Dental Office Relocation IT Checklist for 2026: Before, During and After the Move
The new lease is signed, the movers are booked for a long weekend, and the contractor wants to know where the network closet goes. Meanwhile the old office still has to see patients until Friday afternoon, the phone numbers on every appointment card have to keep ringing, and the pano cannot just go in the back of a truck.
This checklist is for an existing practice moving to a new space, which is a different job from opening a new office. You already have patients, data, phone numbers and equipment that must arrive working. If you are building a practice from scratch, our dental startup IT setup guide runs from the lease to day 90, and the dental startup and new-office IT page explains how that work is planned.
Start the IT side of a dental office move the week the lease is signed: order internet for the new address, confirm the phone numbers can move, cable the new space before the walls close, and book imaging vendors for the pano and CBCT. Move the server last, after a tested backup, and test every room before patients.
- Start IT planning the week the lease is signed: internet, number transfers, cabling and imaging vendors run on other companies' schedules.
- Cable and test the new space before the walls close; Wi-Fi is for tablets and mobile laptops.
- Pano, CBCT and wall-mounted X-ray units are moved by the manufacturer or an authorised dealer; ask your state's radiation control program what paperwork a move needs.
- Move the server last and bring it up first, after a full backup that has been test-restored.
- Test every room before the first patient and keep an issues log for two weeks; do not switch software on move weekend.
In this guide
- When should IT planning start for a dental office move?
- The relocation IT checklist, step by step
- What should be cabled at the new office?
- How do you move internet and phone numbers without losing calls?
- How do you move pano, CBCT and imaging equipment?
- How should the server and data move?
- What should you test in every room before patients return?
- Should you switch software or replace computers during the move?
- Who does what in a dental office move?
- What should you not do when moving a dental office?
- When should you call dental IT about a move?
- What to ask your IT provider about a relocation
- How Legend Networking can help
- Frequently asked questions
- The bottom line
When should IT planning start for a dental office move?
IT planning should start the week the lease is signed, before construction drawings are final. The items that take longest, such as the new internet circuit, phone number transfers, cabling and imaging vendor visits, are booked by other companies on their own schedules. The move itself is the last step, not the first.
| Phase | What has to happen | Why it cannot wait |
|---|---|---|
| Lease signed | Ask internet providers what they can deliver at the new address; ask your phone carrier about moving the numbers | Circuits and number transfers run on the providers' schedules, not yours |
| Drawings | Put the network closet, cable drops per room, imaging equipment and the front desk on the drawings | Changes after the walls close mean opening them again |
| Construction | Cable pulled, labelled and tested; power and cooling for the closet; imaging vendors' site requirements met | Pano and CBCT units have their own room, power and mounting needs |
| Final month | New internet live and tested; equipment list and move order agreed; backup verified | A circuit that is not live on move day leaves the new office offline |
| Move weekend | Server and imaging moved last; everything reconnected and tested room by room | Patients arrive Monday |
| First two weeks | Issues log, fixes, old site closed down | Small problems surface once the schedule is full |
Ask each provider for its lead time in writing and work backward from the first patient day, not from the move date.
The relocation IT checklist, step by step
Work through the move in this order. Each step depends on the one before it: there is no point cabling rooms before the layout is final, or moving the server before the new internet and closet are ready. Tick each step with a name and a date beside it.
Twelve steps from lease to first patient
- 1Inventory what you haveStep 1List every computer, printer, label and receipt printer, sensor, camera, scanner, signature pad, card terminal, phone, camera system and imaging unit, with what it connects to. Mark what moves, what is replaced and what is retired.
- 2Order the internetStep 2Ask providers what they can deliver at the new address and how long it takes. Order the main line and, ideally, a backup line from a different provider.
- 3Confirm the phone numbersStep 3Ask your carrier in writing whether every number moves to the new address, including the main line, fax, text line and any tracking numbers.
- 4Put the technology on the drawingsStep 4Closet location, power and cooling, cable drops in every room, the front desk, Wi-Fi access point positions and imaging equipment.
- 5Book the imaging vendorsStep 5Pano, CBCT and any wall-mounted X-ray units are moved, reinstalled and checked by the manufacturer's service team or an authorised dealer.
- 6Cable the new spaceStep 6Pull, label and test every cable before the walls close, and get the test results and a floor plan with the labels.
- 7Fit out the closetStep 7Rack, switch, firewall, battery backup and access points installed and powered before move weekend.
- 8Bring the new internet liveStep 8Test the new circuit, the backup line and the firewall at the new address while the old office is still open.
- 9Verify the backupStep 9Take a full backup of the server and imaging store before anything is unplugged, and test that it restores.
- 10Move the server and imaging lastStep 10After the last patient at the old office, shut the server down properly, move it, and bring it up first at the new site.
- 11Test every roomStep 11Run the room-by-room test below before the first patient: sign-in, schedule, imaging, printing, payments and phones.
- 12Close the old siteStep 12Cancel or transfer the old internet, collect any equipment left behind, and wipe or destroy drives in anything retired.
What should be cabled at the new office?
Cable every computer that does not move, every imaging workstation, the front desk, phones, printers and card terminals, and a few spare runs in each room. Wi-Fi is for tablets and mobile laptops. Have the cabling tested and labelled before the walls close, and keep the test results with a floor plan.
The dental software makers point the same way. Open Dental says "The usual way of wiring a dental office is with Cat6 cables" and that a wired connection "will be faster, more reliable, more secure, and easier to set up" (Open Dental: Wireless). Henry Schein One's Dentrix System Requirements 2026 list a 1 Gbps network for servers and workstations and say wireless networks "are to be used at your own risk due to potential interference from X-ray machines and other devices."
Drop counts per room, cable category, closet layout and test results are covered in detail in our dental office network setup guide. If you are adding operatories to an occupied office rather than moving, see network cabling when adding operatories. Moves are a good time to fix Wi-Fi dead spots for good; our guide to Wi-Fi that keeps dropping lists what to design out.
How do you move internet and phone numbers without losing calls?
Order internet for the new address as early as possible and have it live and tested before move weekend. Ask your phone carrier in writing whether every number can move with you and on what date. Keep the old lines running until the new ones are confirmed working, and update the 911 address on every phone.
Internet and phone checklist
- Main internet ordered for the new address, with a written install date
- Backup internet from a different provider, ideally on a different type of connection
- Written confirmation from the carrier that every number moves: main line, fax, text line, tracking numbers
- Old internet and phone lines kept until the new ones are confirmed working
- The emergency (911) address updated for every phone at the new location, confirmed with the phone provider
- Card terminals, e-fax, online scheduling and any cloud services checked against the new connection
- Phone menus and after-hours messages updated with the new address
The 911 point is easy to miss. With internet phone systems, the address the provider sends with an emergency call is the address on file, not wherever the phone happens to be plugged in. Ask your phone provider to update it for every handset at the new office and to confirm in writing. If you are changing phone systems as part of the move, our guide to VoIP phone systems for dental offices covers what to plan.
How do you move pano, CBCT and imaging equipment?
Pano, CBCT and wall-mounted X-ray units should be moved and reinstalled by the manufacturer's service team or an authorised dealer, not the general movers. Book them early: they have site requirements for the new room and their own schedules. Sensors, cameras and their capture computers move with IT and are tested before patients.
Ask each imaging vendor four things: what the new room needs (power, mounting, space, cabling), how long removal and reinstallation take, what calibration or checks happen after the move, and what they need from IT, such as the capture computer and its software ready on the network.
Moving X-ray equipment can also mean state paperwork. What a move requires is set by your state, so ask your imaging vendor and your state's radiation control program, and put the answer on the checklist with a name beside it. As an example of where to look, the Texas Department of State Health Services keeps a dental X-ray machine registration page with its own instructions for amending a registration.
For sensors and intraoral cameras, test each one at its new operatory before the first patient using the imaging software's own device test, not a patient exposure. If a sensor will not connect after the move, our guide to an X-ray sensor that stopped working covers the checks, and the imaging integration troubleshooting guide covers the bridge between imaging and the practice software.
How should the server and data move?
Move the server last and bring it up first. Before anything is unplugged, take a full backup of the server and imaging store and test that it restores. Shut the server down properly after the last patient, move it with its battery backup, and confirm the practice software and images open at the new site before setting up workstations.
Server move sequence
- 1Backup and restore testA full backup of the practice database, images and shared files, with a test restore that opens, done days before the move, not the night of it.
- 2Photograph and labelPhotograph the back of the server and closet, and label every cable before unplugging.
- 3Proper shutdownAfter the last patient, close the practice software on every computer, then shut the server down through its own software. Never pull the plug.
- 4Transport with careThe server travels with IT, not in the general load, with its drives and battery backup.
- 5Bring it up firstAt the new site, connect the server to the battery backup and the network, start it, and confirm the practice software and images open from one workstation.
- 6Then the workstationsConnect and test computers room by room once the server is confirmed working.
If your practice software is cloud-based, the server step shrinks, but anything local still moves the same way: imaging stores, scans and the backup of what is kept in the office. Our backup and disaster recovery checklist shows how to prove a backup restores. If shared folders or the X-ray folder do not appear on some computers after the move, our guide to a missing shared drive or X-ray folder covers the usual causes, such as a changed server address.
What should you test in every room before patients return?
Before the first patient, sign in on every computer, open the schedule and a test patient's chart, open images, capture with each sensor using the imaging software's device test, print from each printer, run a card on each terminal, and make and receive a call on each phone. Note every failure on an issues log with a name.
| Area | Test | Pass when |
|---|---|---|
| Every workstation | Sign in; open the practice software and a test patient | Opens at normal speed, correct patient data |
| Imaging | Open existing images; device test on each sensor and camera | Old images open; each device is detected and captures in its room |
| Pano and CBCT | Vendor's post-install checks | Vendor signs off in writing |
| Printers | Print from each computer that uses each printer, including labels and receipts | Correct printer, correct output; see our printer guide |
| Shared folders | Open the shared drive and document areas on every computer | No red X, no path errors |
| Payments | Run a test transaction on each terminal | Approved and printed |
| Phones | Call in and out on each line; check the menu and voicemail | Rings at the right desks; messages correct |
| Internet | Load the cloud services you use; test failover to the backup line if you have one | Works on both lines |
| Wi-Fi | Walk every room with a tablet | Stays connected room to room |
| Cameras, door access, TVs | Check each works | Working and recording where expected |
Keep the issues log for the first two weeks and review it daily with your IT provider. Most move problems are small, but they surface only once the schedule is full.
Should you switch software or replace computers during the move?
Avoid switching practice or imaging software in the same weekend as the move. Each is a project with its own risks, and combining them makes problems harder to trace. Replacing old computers is different: a move is a sensible time to retire hardware that would not be worth moving or that runs an unsupported Windows version.
If a software switch is planned, schedule it before or well after the move and follow our dental software migration checklist. For hardware, the inventory in step 1 is the moment to decide. Henry Schein One notes that "Microsoft's support for Windows 10 ended in October 2025" and that after 30 June 2026 it "will no longer support installing Dentrix on Windows 10" (Dentrix System Requirements 2026). Our guide to whether Windows 10 is still OK in a dental office explains the options for computers that cannot upgrade.
Who does what in a dental office move?
A relocation involves at least six parties, and most problems start where one assumes another is doing a job. Write the owner of every item down. Your IT provider should coordinate the technology parts and make sure each vendor's work fits together, but the practice should know who is responsible for each line.
| Party | Owns |
|---|---|
| The practice | Decisions, the lease, the move date, approving quotes, telling patients |
| IT provider | Inventory, network design, closet, server and workstation move, backups, testing, coordinating the vendors below |
| Internet provider(s) | The new circuit, the modem and the install date |
| Phone carrier | Moving the numbers, the new service and the emergency address |
| Low-voltage contractor | Pulling, terminating, labelling and testing cable (sometimes the IT provider) |
| Imaging vendors | Removing, reinstalling and checking pano, CBCT and X-ray units |
| Practice software vendor | Licensing or support changes for the new address, if any |
| Movers | Furniture and general equipment, not the server or imaging units |
What should you not do when moving a dental office?
The worst move-weekend problems come from a handful of shortcuts. Rule them out at the planning meeting.
Seven things not to do
- Do not cancel the old internet or phone lines until the new ones are confirmed working
- Do not unplug the server without a full backup that has been test-restored
- Do not let general movers pack the server, pano, CBCT or sensors
- Do not close the walls before every cable is labelled and tested
- Do not switch practice or imaging software on the same weekend as the move
- Do not leave old computers or drives behind at the old office without wiping or destroying them
- Do not book patients for the first morning without time for the room-by-room test
When should you call dental IT about a move?
Call three times: the week you sign the lease, so the closet, cabling and internet are planned with the building; before you book move weekend, so the server, imaging and testing fit the schedule; and straight away, during the first two weeks, for anything on the issues log. Report those through the normal helpdesk rather than saving them up; a missing printer or a drive that does not reconnect is quick to fix once reported. Our ticket checklist shows what to include. To see how a dental IT helpdesk handles those calls, read about the Legend helpdesk.
What to ask your IT provider about a relocation
These questions show whether your IT provider has planned a dental move before. Ask them at the first planning meeting and get the answers in writing.
Planning
- Who coordinates the internet provider, phone carrier, low-voltage contractor and imaging vendors, and how will we see the schedule?
- What do you need on the construction drawings, and by when?
The move
- When will you take and test the final backup, and who signs it off?
- In what order will the server, workstations and imaging come up at the new site?
After the move
- Who runs the room-by-room test, and what happens to items that fail?
- What happens to the computers and drives we retire?
The contract
- Which parts of the move are in our monthly fee, and which are quoted separately: cabling, new hardware, vendor coordination, after-hours move-weekend work?
- Is a copy of the final pre-move backup kept offline or air-gapped until the new site is signed off?
- Is our business associate agreement (BAA) signed and current before you transport a server holding patient records?
How Legend Networking can help
Legend Networking has 22+ years in dental IT and has served over 3,500 practices since 2004. Legend supports the IT environment around Dentrix, Eaglesoft, Open Dental and Archy and the imaging systems DEXIS, Vatech, Carestream, Planmeca/Romexis and Dolphin Imaging. Onsite dispatch is by appointment across served dental markets, and support is remote-first nationwide. Hardware procurement, major cabling projects and software licensing are quoted separately. Examples of new-office and build-out projects are on our work page.
The author, Ian Lynch, has 22 years in dental IT and oversees the NOC, onsite dispatch and client technology roadmaps. Legend holds a 4.8 rating from 173 Google reviews.
Frequently asked questions
How early should IT planning start for a dental office move?
Start the week the new lease is signed, before construction drawings are final. The new internet circuit, phone number transfers, cabling and imaging vendor visits are all booked by other companies on their own schedules, so they set the timeline. Ask each provider for its lead time in writing and plan backward from the first patient day.
Can we keep our phone numbers when the office moves?
Often yes, but confirm it with your carrier in writing before you sign anything, because it depends on the carrier, the type of line and how far you are moving. List every number: the main line, fax, text line and any tracking numbers. Keep the old service running until each number is confirmed working at the new office.
Who moves the pano and CBCT?
The manufacturer's service team or an authorised dealer, not general movers. They remove, transport, reinstall and check the unit, and the new room has to meet their site requirements for power, mounting and space. Book them early, and ask them and your state's radiation control program what paperwork the move needs.
Should we move the old server or buy a new one?
It depends on its age, warranty and the Windows Server version it runs. A server near the end of its support is often better replaced as part of the move than moved and replaced a year later. Whichever you choose, take a full backup and test that it restores before anything is unplugged. Ask your IT provider for a written recommendation.
Can we see patients the day after the move?
Yes, if the move is planned that way: new internet live in advance, cabling tested, the server moved last and brought up first, and a room-by-room test done before patients arrive. Leave time on the first morning for the test and fixes. Booking a full schedule for the first hour after a weekend move leaves no room for small surprises.
Do we need new cabling at the new office?
Usually yes, unless the space was a dental office recently and its cabling is documented and tested. Old cabling of unknown quality causes intermittent faults that are hard to trace. Have every run tested and labelled before the walls close, and plan cable drops per room for computers, imaging, phones, printers and access points rather than relying on Wi-Fi.
What happens to equipment we leave behind?
Anything that stored data, such as old computers, servers, copiers and storage boxes, should have its drives wiped or destroyed, with a record of what was done. Do not leave them at the old office or hand them to a recycler without that step. Your IT provider should list what is retired in the inventory and confirm how each item's data was removed.
Is a relocation the same as opening a new office?
No. A new office starts with no data, no patients and no phone numbers. A relocation has to move all three without losing any, while the practice keeps seeing patients until moving day. The building work is similar, so the cabling and closet planning overlap, but the server move, number transfers and testing are what make a relocation its own project.
The bottom line
Bring your new floor plan and your move date to your IT provider, and ask for the twelve-step checklist above with an owner and a date beside every line. To see how dental office build-outs and new-office technology are planned, read about our dental office build-outs and dental startup and new-office IT.