Dental Office Fit-Out in New York City: IT Decisions Before the Walls Close
The broker found it: 1,400 square feet on the fourth floor of a Midtown building, five operatories if the plan is tight. Then the welcome packet arrived. In this building, contractors work after 6 p.m. only, with a certificate of insurance on file first. Nobody had mentioned the internet line yet.
Read it alongside our New York City dental IT guide; what Legend offers city practices is on its page for New York City dental IT services. This guide covers only that building layer: the landlord, the managing agent, the riser and the carrier. For everything that is the same in any city, such as the system list, the room-by-room plan and the budget, it points you to the national guides. If you are opening a dental practice in NYC for the first time, or moving an existing one into a new suite, read it before the work letter is signed.
In a New York City dental office fit-out, the building decides more of your IT plan than the floor plan does. Before design is final, find out the riser route, the carriers already in the telecom room, the closet spots the building accepts and the hours work is allowed. Those answers set the cabling, internet and opening dates.
- A New York building is a stakeholder in your fit-out: it decides work hours, insurance paperwork, elevator access and who opens the telecom room.
- Raise the IT items while you still have leverage, before signing and while the work letter is drafted.
- The closet and cable routes follow the building's answers on carrier entry, riser access, cooling and permitted work hours.
- Put every account, from the internet line to the building portal, in the practice's name before opening day.
- New practices are custom quoted; ask each provider to state what its price assumes about after-hours work and carrier entry.
In this guide
- What makes a dental office fit-out in a Manhattan, Brooklyn or Queens building different for IT?
- What should you settle with the landlord before you sign or during the work letter?
- Which building questions decide where the network closet and cabling go?
- When does each IT task happen during a NYC dental office fit-out?
- How do you get internet into the suite on time?
- Who owns which account on opening day?
- What about imaging, practice software and phones in a small Manhattan or Brooklyn suite?
- What does IT for a new dental office in New York City cost, and how is it quoted?
- What can Legend show a practice opening in New York City?
- What to ask your IT provider before a New York City fit-out
- Sources
- Frequently asked questions
- The bottom line
What makes a dental office fit-out in a Manhattan, Brooklyn or Queens building different for IT?
A New York building is a stakeholder in your project. Its managing agent can decide when contractors work, what insurance they show, how equipment reaches your floor and who opens the telecom room, so ask for its rules. Space is tight, the internet path is shared, and your suite shares walls, ceilings and closets with neighbours.
In a suburban strip or a standalone building, the dentist, the architect and the general contractor run the project, and the IT provider fits in around them. In Manhattan, Brooklyn or Queens there is a fourth party with its own calendar and its own rules: the building. Four things follow from that.
The path in is not yours. In a multi-tenant building, the internet line generally reaches a suite from a shared telecom room through a riser; ask where that room is, because in some buildings it sits in the cellar. You may not control that room, may not hold its key, and may not be able to choose any carrier you like. Your IT plan starts with what the building already has.
The window to work may be narrow. A building can limit noisy or disruptive work to evenings or weekends and ask for notice before elevators and deliveries are used; ask whether yours does. Those rules affect when cable can be pulled, when a carrier technician can reach the riser and when equipment can be carried up. They also affect cost, because after-hours labour is priced differently. Ask the building for its rules in writing rather than assuming them.
Space is the most expensive thing in the suite. Every square foot given to a network closet is a square foot not given to an operatory or a sterilization area. The pressure is to put the network in a supply cupboard or above a ceiling. That can work, but the equipment still needs air, power, a door that locks and room for someone to service it.
The building type changes the questions. A full-floor suite in a Midtown tower, a medical suite in a co-op or condo building on the Upper East Side, and a former storefront on a commercial avenue in Bay Ridge or Astoria each have a different riser story, a different landlord relationship and different limits on what you can attach to the roof or the window. The table below is a starting point for what to ask, not a description of any particular building.
| Building type you might be looking at | What tends to be shared | Questions that matter most for IT |
|---|---|---|
| Commercial office tower (Midtown, downtown, Long Island City) | Telecom room, risers, freight elevator, loading dock, building engineer | Which carriers are already in the telecom room; who books the riser and the elevator; contractor insurance and work-hour rules; whether your suite gets its own conduit to the riser |
| Medical suite in a co-op or condo building | Board or managing agent approval, residential neighbours, shared mechanical spaces | Whether the board must approve alterations and contractors; quiet hours; whether a new carrier can enter at all; where the suite's line terminates today |
| Ground-floor retail or former storefront (outer-borough avenues) | Cellar space, sometimes a meter room shared with upstairs tenants | Where the existing line enters the cellar; whether the cellar floods or is damp; whether the landlord allows a new entry through the façade or sidewalk; who controls the cellar key |
| Second-generation dental suite (a previous dental tenant) | Existing cabling, closets and plumbing left behind | Whether the old cabling is documented and tested; who owns equipment left in the closet; whether the previous carrier account was closed or transferred |
What should you settle with the landlord before you sign or during the work letter?
Raise the IT items while you still have leverage, before signing and while the work letter is drafted. Ask who pays for a carrier entry, whether you may use the riser and telecom room, where your closet can go, what cooling and power the suite gets, and which rules bind your vendors. Your broker and lawyer handle the wording.
The work letter, or the tenant-improvement exhibit attached to the lease, is where the landlord's work and the tenant's work get divided. It is a legal and commercial document, and the decisions about it belong to you, your broker and your lawyer. What an IT provider can do is give your broker and lawyer the list of technology items that should be discussed while they are still negotiable. After the lease is signed, each of these becomes a request rather than a term.
Items worth putting on that list:
- Telecom access. Whether the lease gives the tenant the right to bring a carrier of its choice into the building, and the right to use the riser and the telecom room to reach the suite. If the building has agreements with particular carriers, ask which ones and whether others are allowed.
- Who pays for the path. If a new carrier has to build into the building, or if conduit has to be run from the telecom room to your floor, find out whether that is landlord work, tenant work or shared.
- Closet location and conditions. Whether the space you want for the network closet can have its own cooling or ventilation, and whether the building's air system runs after hours or on weekends. Ask whether the building's cooling runs at night; a closed closet holding network equipment keeps producing heat when the office is empty.
- Electrical capacity. Whether the suite's electrical service can carry the imaging equipment, the compressor and vacuum, the workstations and a battery backup for the network. Your architect and electrician answer this; the IT plan needs the result.
- Roof or window rights. If you want a cellular backup line with an outside antenna, whether the landlord permits one and where.
- Contractor rules. The building's rules for contractors, attached or referenced in the lease, so everyone quoting the work prices it with the rules in mind.
- Access after opening. Whether your IT provider can be added to the building's access list for future visits, including evenings, and how that is requested.
- Flood exposure. If the telecom room or the cellar sits in a low-lying part of the city, check the address in the NYC Emergency Management Hurricane Evacuation Zone Finder. Zone 1 carries the highest flood risk of the city's six zones, and the zone map is separate from FEMA's flood insurance map. If the line enters a cellar in zone 1 or 2, ask what the building does to protect it. Our guide to planning for power outages in a New York City dental office covers the outage side.
None of this is legal advice. It is a list of technical facts your advisers need so they can decide what to ask for.
Which building questions decide where the network closet and cabling go?
The closet and the cable routes follow the building's answers: where the carrier line enters, how it reaches your floor, which walls and ceilings you may open, how hot the space runs and when work is allowed. Ask building management these questions in writing before the architect fixes the closet and the electrician fixes circuits.
General guidance on where the IT room goes in a dental office design and on dental office network setup and cabling applies in New York too; read both. What is particular to a New York building is that some of the answers come from the managing agent or the building engineer, not from your own team. Network cabling for a NYC dental office is routed around a building you do not control, so the routes are decided by the answers below. A dental office build-out in Manhattan, Brooklyn or Queens rarely gets to choose its own path to the street.
Questions for building management
Send these as one list, early, and keep the replies with your project file. Building rules vary widely; nothing here describes what any building requires.
- Insurance certificates. What certificate of insurance does a contractor need before working in the building, what limits, and who must be named on it? Does this apply to the IT provider and the carrier's installer, not only the general contractor?
- Freight elevator. How is the freight elevator booked, how far ahead, and are there time limits or fees? Is a building staff member needed while it runs?
- Permitted work hours. Which kinds of work are limited to evenings or weekends? Does cable pulling above a ceiling count as noisy work in this building?
- Riser access. May our installers run cable through the riser to our floor, and do the existing sleeves or conduit have room left?
- Telecom room keys. Who holds the key to the telecom room, and how do our installer and the carrier's technician get in? Does someone from the building have to be present?
- Existing carriers. Which internet carriers already have equipment in the building, and where do they terminate: the cellar, a telecom room on our floor, or somewhere else?
- New carrier entry. If we want a carrier that is not already here, does the building allow a new entry, what approval is needed, and who pays for it?
- The demarcation point. Where does the carrier's responsibility end and ours begin for this suite? Is there an existing line or wiring from the telecom room to our suite, and is it documented?
- Antenna rights. May we place a small cellular antenna on the roof or at a window for a backup internet line? What approval does that need?
- Closet cooling. Does the building's cooling run nights and weekends? May we add supplemental cooling or ventilation for a small network closet, and what does the building require for it?
- Electrical capacity. What electrical service does the suite have, and can it be increased if the imaging equipment and battery backup need more? Who in the building signs off on that?
- Ceiling and wall work. Which ceilings and walls inside the suite are ours to open? Are there fire-rated walls or shared ceilings where penetrations need building approval?
- Work-plan submission. Does the building want a written work plan or drawings from the IT contractor before work starts, and how long does review take?
- Future access. After we open, how do our IT provider and our carrier get into the building and the telecom room for a visit or a repair, including in the evening?
- Shutdown notices. How does the building tell tenants about planned power, cooling or water shutdowns, and can our office manager and IT provider both be on that notice list?
- Old equipment. Is there wiring, a closet or carrier equipment left by a previous tenant that we are expected to keep, remove or take over?
For anything about filings or approvals the work itself needs from the city, ask your architect or general contractor which filings apply. The answer depends on the building and the scope, and it is theirs to give.
When does each IT task happen during a NYC dental office fit-out?
The IT work rides on the building's calendar. Before signing, you confirm the path in. During the lease and design you settle closet, power and carrier. While walls are open, cable goes in during the building's permitted hours. The carrier install, the move-in and the first test patient follow. Each stage has one building question that must be answered first.
The table is organised by stage, from before the lease is signed to the first patient. For each stage it gives the building question to settle, who can answer it, what the IT plan needs from the answer, and what usually goes wrong when the question is skipped. It is a coordination map, not a schedule: how long each stage takes depends on the building, the contractor and the carrier.
| Stage | Building question to settle | Who answers | What the IT plan needs from it | What goes wrong if it is skipped |
|---|---|---|---|---|
| Before signing | Which carriers are in the building today, and would the building accept another? | Building management, broker; a lookup of the address on the FCC map | A realistic main line and a second path for backup | You sign for a suite where the only available line does not suit imaging or cloud software, and a new entry is refused or costly |
| Lease negotiation (work letter and exhibits) | Riser and telecom-room rights, who pays for a new carrier entry, closet cooling, roof or window rights | Landlord, your broker and lawyer, with technical input from IT | Written access to the path in, a closet you are allowed to cool, an agreed answer on cost | Each item becomes a favour you ask for later, after your leverage is gone |
| Design | Where the suite's line terminates; which walls and ceilings may be opened; electrical capacity for imaging and battery backup | Architect, building engineer, electrician, IT | Closet location, cable routes, dedicated circuits and the device list per room | The closet ends up where the carrier cannot reach, or the circuit list misses the network rack |
| Construction (walls open) | Permitted work hours, insurance certificates on file, freight elevator bookings, riser access for the cable pull | Building management, general contractor, IT cabling contractor | A cable pull scheduled inside the building's windows, with every installer approved in advance | The cabling crew is turned away at the lobby, or the pull is pushed to weekends the contractor did not price |
| Close-in (before ceilings and walls are finished) | Inspection of cable runs and labels; any penetrations through rated walls approved | General contractor, IT, building engineer | Every drop tested and labelled; a record of where each run goes | Adding a missed drop means opening finished walls, with another building approval |
| Carrier install | Who lets the carrier into the telecom room, and is the riser path ready? | Building management, carrier, IT | The line extended from the demarcation point to your closet and handed over working | The carrier's technician arrives, cannot get into the telecom room, and the visit is rescheduled with the opening date behind it |
| Move-in | Elevator bookings for furniture and equipment; delivery hours; protection for finished floors | Building management, equipment dealer, movers | Workstations, imaging units and network equipment delivered and in place | Deliveries collide with the building's other tenants and equipment sits in the lobby |
| First patient | Building access for your IT provider on opening day; who to call in the building if power or cooling fails | Building management, office manager | A named building contact and an access arrangement for the first weeks | A problem on day one waits for a building staff member who is not on duty |
For the full stage-by-stage startup plan that applies anywhere, see the full dental startup IT guide. This table adds only the building column that a New York suite needs.
How do you get internet into the suite on time?
Start with the address, not a price sheet. Find out which carriers already serve the building, where their lines end and whether the riser path to your floor is clear. Order early, give the carrier the building's access rules, and plan a backup path. The install date is set by the carrier and the building, not by you.
The internet line is the item most likely to hold up a New York opening, because it depends on three parties: the carrier, the building and your own cabling. Four steps reduce that risk.
- Look up the address. Search the address on the FCC National Broadband Map to see which providers report service there. Then ask building management which of them actually have equipment in the telecom room. The two lists do not always match.
- Order once the lease is signed. Give the carrier the suite number, the building contact and the building's rules for contractors, including any insurance certificate requirement, so the technician's visit is not refused at the door.
- Get the path ready first. Before the carrier's visit, confirm that the cable from the telecom room to your closet is in place and tested, or that the carrier will run it.
- Plan a second line. A backup from a different carrier, or a cellular line, gives the practice a way to keep working if the main circuit fails. Where the backup comes from depends on what the building allows, which is why the antenna question belongs on the building list.
Picking the primary circuit and its fallback around imaging and cloud software gets its own treatment in our NYC dental office internet guide.
Who owns which account on opening day?
The practice should own every account and hold every administrator login on opening day, including the ones created by the building, the carrier and the contractors during the fit-out. Write down whose name each account is in, who created it, where the credentials are kept and what the building has on file for it.
A fit-out creates logins quickly and in many hands. The general contractor signs up for the building's work-order portal, the carrier opens the internet account, the dealer installs imaging software, and the IT provider sets up the firewall. On opening day, you want each of those in the practice's name, with the credentials somewhere the owner controls. In a New York building there are a few extra items that national checklists leave out: the building's systems, the access cards and the carrier's relationship with the building.
| Account or login | Should be in the name of | Usually created during the fit-out by | Where the credentials sit on opening day | Building tie-in to check |
|---|---|---|---|---|
| Building tenant portal (work orders, elevator bookings, visitor lists) | The practice, with the office manager as a named user | General contractor or the owner during the build | Owner's password manager; contractor's access removed after move-in | Who on the building's side can reset it |
| Building access cards and after-hours access list | The practice | Building management | A written list of cardholders kept by the office manager | Whether the IT provider is listed for evening visits |
| Main internet account | The practice entity | Carrier, often ordered by the IT provider or contractor | Account number and business support number in the practice's records | Whether the carrier needs the building's permission for each visit |
| Backup internet or cellular line | The practice entity | IT provider or carrier | Same record as the main line | Any antenna permission granted by the landlord, filed with the lease |
| Domain name and DNS | The practice entity | Web designer or IT provider | Owner holds the administrator login | None, but list it so nothing is missed |
| Microsoft 365 or other email | The practice | IT provider | Owner holds an administrator account of their own | None |
| Practice management software licence (for example Dentrix, Eaglesoft, Open Dental or a cloud system such as Curve or Denticon) | The practice | Software vendor | Licence agreement and top-level admin login in the owner's records | None |
| Imaging software licences | The practice | Equipment dealer | Licence keys listed against each workstation | None |
| Firewall and switch administration | The practice, with the IT provider as an additional administrator | IT provider | Owner can see who has admin rights | Where the firewall sits relative to the building's demarcation point |
| Wi-Fi (staff and guest networks) | The practice | IT provider | Network names and admin login recorded | Whether the building runs its own Wi-Fi that could overlap |
| Suite door access and cameras | The practice | Security or low-voltage contractor | Admin login with the owner | Whether the suite system must link to the building's lobby system |
| Telecom room and riser contact | Not an account; a person | Building management | Name and phone number of the building engineer or super | Who to call when the carrier needs the room |
The national guide keeps the general version of this register. The rows that matter in New York are the first two and the last one, because they are the ones you cannot recreate yourself.
What about imaging, practice software and phones in a small Manhattan or Brooklyn suite?
A small New York suite still carries a full dental system: practice software, imaging sensors and units, phones, printers and the network. Choosing cloud software reduces what lives in the closet but makes the internet line matter more. Imaging units, battery backup and network gear still need power, air and space you plan for during the fit-out.
The software and imaging choices are the same as anywhere. What changes in a tight suite is where everything physically goes.
- Practice software. Many new practices compare a server-based system with a cloud system. With a server, the closet holds a computer that stores patient data and needs cooling, battery backup and a backup routine. With cloud software, the closet is smaller, but the internet line becomes the thing every chair depends on, which is one more reason to settle the backup path with the building.
- Imaging. Sensors, intraoral cameras, panoramic and cone-beam units come with the manufacturer's site requirements for power and data. Pass them to your architect and electrician during design, not after. Imaging files are large, so plan where they are stored and how they are backed up.
- Phones. Internet-based phone systems run over the same network and the same line. If the line is down, so are the phones, unless calls fail over to mobiles or a second line.
- Heat. A closet holding a firewall, switches, a phone system, a battery backup and possibly a server produces heat around the clock. If the building's cooling runs only in business hours, the closet needs its own answer.
On the software side, the platforms whose IT environment Legend supports are Dentrix, Eaglesoft, Open Dental and Archy, with DEXIS, Vatech, Carestream, Planmeca/Romexis and Dolphin Imaging on imaging. Our page on practice management software and imaging support explains that support, and the city version, dental software and imaging support in New York City, covers what changes for sensors and scans in a city suite.
What does IT for a new dental office in New York City cost, and how is it quoted?
New practices are custom quoted, because the scope depends on the suite, the systems and the building. In a New York building, after-hours work, extra cabling runs and a new carrier entry can each change the quote, so ask every provider to state in writing what its price assumes.
We do not publish New York fit-out costs, because no honest single number exists. Two suites of the same size can differ a great deal depending on whether cable can be pulled during the day, whether the riser has room, whether a carrier has to build into the building and whether the closet needs its own cooling.
What you can do is make each quote comparable. Ask every contractor and IT provider to state:
- whether their price assumes daytime or after-hours work, and what changes if the building limits hours;
- how many cable drops are included and what an added drop costs once walls are closed;
- whether the carrier's installation and any new building entry are inside or outside their price;
- which insurance certificate they will provide to the building, and whether that is included;
- what hardware, licences and monthly services are listed separately.
For the line items a new practice should budget for, see our dental startup IT budget guide. For how Legend approaches new practices, see our page on dental startup IT.
What can Legend show a practice opening in New York City?
Legend has served over 3,500 practices since 2004. The nearest published projects to New York City are openings in Ambler, Pennsylvania; Middletown, Delaware; and Jessup, Maryland. Legend is headquartered in Dallas, and none of its published projects is in New York yet.
The nearest published projects. These are openings Legend has documented on its own project pages. None is in New York; each is named in its own city, in the words of its project page:
- Maple Glen Modern Dentistry, Ambler, Pennsylvania: "Legend worked alongside Dr. Adam Rudin from early concept and planning through the opening of Maple Glen Modern Dentistry."
- Calm Family Dental, Middletown, Delaware: the June 2024 project update "features Dr. Nwokolo's Calm Family Dental in Middletown as the final details came together ahead of opening."
- Smile Craft Orthodontics, Jessup, Maryland: "Smile Craft Orthodontics is now open in Jessup, Maryland. Legend Networking supported the startup launch by helping establish a reliable, secure technology foundation designed for smooth day-one operations".
The company facts. Legend has 22+ years in dental IT (since 2004) and reports a 4.8 rating · 173 Google reviews. It works with in-house engineers; no outsourced first-level triage.
How that meets a New York building. Whoever you hire, the questions in this guide matter: building access, insurance certificates and work windows have to be arranged ahead of any contractor's work in your suite. Ask every provider, Legend included, how work in your building would be arranged before you rely on it. For Legend's offer to practices across Manhattan, Brooklyn, Queens, the Bronx and Staten Island, see its page as a dental IT company in New York City.
What to ask your IT provider before a New York City fit-out
Ask these before you sign with an IT provider for a New York fit-out. They test whether the provider has thought about the building, not only the equipment.
- Which questions will you want us to put to building management, and when do you need the answers?
- Will you review the work letter's technology items with our broker and lawyer before we sign?
- What insurance certificate can you provide to our building, and can you name the building's managing agent on it?
- Does your cabling quote assume daytime or after-hours work, and what changes if the building restricts hours?
- How will you find out which carriers are already in our telecom room, and what do you do if the one we want is not?
- Who meets the carrier's technician at the telecom room, and who arranges building access for that visit?
- Where would you put our network closet in this suite, and how will it stay cool when the building's air is off?
- What equipment will sit in the closet, and how much power and battery backup does it need?
- What backup internet path would you recommend for this building, and does it need an antenna or landlord approval?
- Which accounts will you create during the fit-out, and in whose name?
- How will a future visit to our building be arranged, given the building's access rules?
- What will you hand us at opening: cable labels and test results, a closet diagram and a list of every login?
Sources
- NYC Emergency Management, Hurricane Evacuation Zones (six zones; zone 1 most likely to flood; use the Zone Finder or call 311; distinct from FEMA flood insurance zones). Accessed 23 October 2026.
- NYC Emergency Management, Utility Disruptions (which electric utility serves which part of the city). Accessed 23 October 2026.
- Federal Communications Commission, National Broadband Map (search an address for reported fixed-broadband providers). Accessed 23 October 2026.
- Legend Networking project pages for Maple Glen Modern Dentistry, Calm Family Dental and Smile Craft Orthodontics (linked above).
Frequently asked questions
When should IT get involved in a Manhattan dental office fit-out?
Before the lease is signed, if possible. The questions that shape the IT plan, such as which carriers reach the building, whether a new one can enter, and where the closet can go, are easiest to settle while the work letter is still being negotiated. After signing they become requests to the landlord instead of terms, and design may already have fixed the closet.
Who decides where the network closet goes in a leased suite?
You and your architect choose the location, but the building shapes the choice. The closet has to be reachable from the riser or the telecom room, allowed to have cooling or ventilation, and served by enough power. Ask building management where the suite's line terminates and what cooling rules apply before the architect fixes the closet on the plan.
Does a Midtown or Brooklyn office building have to let a new internet carrier in?
That depends on the building and the lease, so ask rather than assume. Ask building management which carriers already have equipment in the telecom room, whether a new carrier entry is allowed, what approval it needs and who pays. If carrier choice matters to you, raise it with your broker and lawyer during the lease negotiation, when it can still be written in.
Why does the building want an insurance certificate from our IT contractor?
A building that asks for a certificate of insurance wants evidence that anyone working on its premises carries cover it accepts. Whether yours asks, which limits apply, who must be named, and whether IT cabling crews and carrier installers are included are the building's decisions. Ask for the requirement in writing early and pass it to every vendor who quotes.
Can dental office cabling be done after hours in a Manhattan or Queens building?
That is for the building to say, and it may even prefer evening work when ceilings are opened. Ask building management which work is limited to evenings or weekends and how to book access. Then ask each contractor whether their price assumes daytime or after-hours work, so the quotes you compare are on the same basis.
Should a new New York practice start with a server or cloud software?
Both can work. A server needs a cooled, powered and backed-up closet, which costs space in a small suite. Cloud software makes the closet smaller but makes the internet line, and its backup, the thing every chair depends on. Decide early, because the answer changes the closet, the power and the internet plan you agree with the building.
Who should own the internet account, the practice or the landlord?
The practice, in most cases. The internet account, its account number and the carrier's business support number should be in the practice's name, so you can change service, add a backup or move without the landlord's help. If the building supplies the connection, ask what happens when you need a repair, an upgrade or a second line.
How much does IT cost for a new dental practice in New York City?
New practices are custom quoted, because the scope depends on the suite, the systems and the building's rules. Once the office is open, Legend's ongoing plans are listed as starting at $360 per month. In a New York fit-out, after-hours work and a new carrier entry can change a quote, so ask each provider to state in writing what its price assumes.
Which of Legend's published practice openings are nearest to New York City?
They are startup openings in three other states: Ambler, Pennsylvania (Maple Glen Modern Dentistry), Middletown, Delaware (Calm Family Dental) and Jessup, Maryland (Smile Craft Orthodontics), each with its own project page. None is in New York, so before you sign with any provider, ask it for an opened practice you can phone as a reference.
The bottom line
Relocating an established practice into a new building? Begin with the systems you already run. We invite you to request a Free Dental IT Assessment: it reviews your computers and software, network security, backups and performance, and you receive written findings with prioritized recommendations to carry into the new suite. If you are opening from scratch, bring the floor plan, the building's contractor rules and your target opening date to a planning conversation.