Dental Office Finish-Out Inspections in Frisco and Prosper: The Gates That Set Your Technology Dates

A dentist has two suites on the table and one letter-of-intent deadline. One is a cold shell in a new building in Frisco or Prosper. The other is a second-generation dental suite in Plano, offered as an equipment purchase and lease assumption. The broker and the contractor talk about rent, square feet and plumbing. Nobody has mentioned the state registration, or the inspection that decides when the data cable has to be in.

For help after opening day, Legend's page on dental IT support in Dallas–Fort Worth sets out how ongoing support is arranged. This piece belongs to our Collin County dental IT guide and covers one narrow job: the registration and inspection gates of a dental finish-out, and what the technology side must have done before each one. Your architect files, your general contractor books inspections, and your IT provider plans to their dates. Nothing here is legal advice, and the city and the state are the authorities on their own rules.

In this guide
  1. Cold shell or second-generation dental suite: which one makes the inspection gates simpler?
  2. Gate 1: Does your finish-out have to be registered with TDLR, and what does that change for the technology?
  3. What do two public Frisco dental finish-outs show about the schedule?
  4. Gate 2: What has to be on the drawings before plan review in Frisco, Prosper or Allen?
  5. Gate 3: When does cable have to be finished before the above-ceiling inspection in a Frisco or Prosper build?
  6. The inspection-gate calendar: what must IT have done before each gate?
  7. Gate 4: What must not move between the final inspection, the certificate of occupancy and the RAS inspection?
  8. Which gate did each Collin County build have to meet?
  9. Who installs the cameras and door access, and what should you ask before the ceiling closes?
  10. What should the GC, the low-voltage contractor and the IT provider agree in writing about the inspection schedule?
  11. How do you choose an IT provider for a Collin County finish-out?
  12. What to ask your IT provider before the first inspection
  13. Key takeaways
  14. Sources
  15. Frequently asked questions
  16. The bottom line

Cold shell or second-generation dental suite: which one makes the inspection gates simpler?

A cold shell is simpler to plan for, because every cable route, the closet and the circuit entry are yours to decide before the first drawing. A second-generation suite can be quicker, but only if what the last tenant left passes a test before your own permit and inspection dates arrive. The gates apply to the work you change, so the more you re-plan an old suite, the more it behaves like a cold shell.

Listings in Frisco and Plano in late 2026 advertise both kinds of space: shells in new buildings offered for a tenant's custom build-out, and former dental suites offered with their equipment. The growth north of the metro keeps the choice coming up. In the Census Bureau's estimates for July 2024 to July 2025, Celina was the fastest-growing US city of 20,000 or more people, and Princeton, Melissa and Anna were third, fourth and fifth. Each of those towns lies at least partly in Collin County, and every new dental office there passes through the same gates.

Table A. Cold shell vs second-generation suite, seen through the inspection gates

Cold shell (new building)Second-generation suite, minor changesSecond-generation suite, re-planned
What you controlEvery cable route, the closet location, the circuit entry point, the ceiling layoutVery little behind the walls; mostly what you add at the desk and the chairThe rooms you rebuild, and the cable you pull to them
What you inheritNothing but the building's entry points and its rules for contractorsOld cable, an existing closet, conduit, perhaps a server room you did not designThe same as minor changes, in the rooms you do not touch
Which gates applyAll of them: TDLR registration if the estimated cost is $50,000 or more, the city permit and every inspectionA city permit and inspections for the work you change; TDLR registration only if the cost reaches $50,000Usually all of them, because a re-plan rarely stays under $50,000
Schedule riskLong, but predictable; the cable date follows the ceiling inspectionShort on paper; the risk is finding failed cable after you have signedThe worst of both if the inherited cable is only tested after the ceiling inspection
What the IT provider must see firstThe floor plan, before the architect's drawings go to reviewThe existing closet and a test of every inherited cable runBoth: the floor plan for new rooms and a cable test for old ones

Two readings of the table matter most. First, the $50,000 threshold is low for a dental finish-out. The two public Frisco filings in the worked example below estimate $190,000 and $221,000. Second, a second-generation suite only saves time if the old cable passes before the first inspection that would cover it. Test it while the ceiling is still open. If you plan to keep and extend the old network, our guide to cabling an existing office covers how added rooms join it.

Gate 1: Does your finish-out have to be registered with TDLR, and what does that change for the technology?

In Texas, a project with a total estimated cost of $50,000 or more is registered with the Texas Department of Licensing and Regulation and reviewed and inspected by a Registered Accessibility Specialist. Your architect handles the filing; the IT question is what has to be in place before each inspection. For the technology, the registration fixes a set of drawings that a reviewer has seen.

What the rule text says. TDLR's own Architectural Barriers FAQ puts it this way: "Projects with costs of $50,000 or more are required to submit a full set of construction documents in accordance with Administrative Rule 68.50." For smaller projects, the same answer says they are not required to be submitted for registration and review, "however, the project is still required to comply with TAS," the Texas Accessibility Standards.

The question for your architect. "Is this finish-out registered with TDLR, who is the Registered Accessibility Specialist, and which drawing set did they review?"

What it changes for the technology is narrow, and it is about placement. The front desk, the check-in point, a kiosk or tablet stand, a patient-facing monitor and the counter equipment are all drawn on the plans the reviewer sees. If the IT plan later moves a check-in kiosk, swaps a counter monitor for a wall-mounted arm, or adds a printer stand in a corridor, that is a change to drawn items. Keep the technology placed as drawn, and if something must move, tell the architect before it moves, not after.

This guide does not describe accessibility requirements, and the IT provider should not interpret them either. The practical rule is simpler: once the drawings are registered, the IT plan follows the drawings.

What do two public Frisco dental finish-outs show about the schedule?

TDLR's project registry is public, and Frisco dental finish-outs appear in it. Two records opened on 28 November 2026 show estimated costs of $190,000 and $221,000, listed durations of about five and a half months and about fourteen months, and scope lines that do not mention data cabling at all. That last point is the useful one: the technology work runs beside the listed scope and must still meet its inspection dates.

Here are the two filings, unnamed, as they read on the registry:

Worked example B. Two public TDLR filings for Frisco dental finish-outs

Filing 1: dental office renovation, FriscoFiling 2: dental office finish-out, Frisco
Size3,400 square feet1,886 square feet
Estimated cost$221,000$190,000
Cost per square foot (our arithmetic)about $65about $101
RegisteredMarch 6, 2025October 23, 2025
Listed start → completionJuly 21, 2025 → September 22, 2026November 17, 2025 → April 30, 2026
Listed duration (our arithmetic)about 61 weeksabout 23 weeks
Gap from registration to startabout 4.5 months25 days
Scope as filednon-structural partitions, two restrooms, mechanical supply and return, plumbing, T-bar ceiling, lights, outlets, switches"Dental office finish out"
Status on the registryReview CompleteProject Closed
Data cabling, cameras, AV or a network closet in the scope linenot listednot listed

What the two records tell an owner choosing a suite:

    1. Both are far above the $50,000 threshold. A dental finish-out of any real size will almost always be registered, so plan for the registration gate from the start.
    1. The listed dates are estimates. They are what someone entered on a form, and the longer record's completion date may reflect a slow start, phased work or a conservative guess. Do not read either as a prediction for your own suite. Timelines vary with the building, the contractor and the city.
    1. The technology is invisible on the form. The longer scope lists the T-bar ceiling and the outlets, the two things the data cable must work around, and says nothing about the cable itself. Nobody filing the form is responsible for your network. Someone still has to make sure the cable is in before that T-bar ceiling is inspected and closed.

The back-calculation, as an example. Take a 23-week finish-out like Filing 2, and suppose, for this example only, that the GC books the above-ceiling inspection for week 12. Count back from that date:

Week (example)What has to be doneWhy
Week 6Equipment list final: every workstation, imaging device, camera, screen, printer and phone, by roomThe cable drawing is counted from it
Week 8Cable drawing approved by the practice and the GCThe low-voltage contractor needs it to price and schedule the pull
Week 11Data, camera and AV cable pulled, labelled and testedThe ceiling inspection is next week; nothing is added after it without reopening tiles
Week 12Above-ceiling inspectionThe GC's date, which the IT schedule follows
Week 23Final inspection and certificate of occupancyWorkstations, imaging and phones installed and tested before it

The numbers in that table are an example, not a schedule. The pattern is what carries over: if the ceiling inspection is booked for week N, the cable pull finishes in week N−1, which means the cable drawing is approved by N−4 and the equipment list is fixed by N−6. Ask your GC for the real week N as soon as the construction schedule exists.

Gate 2: What has to be on the drawings before plan review in Frisco, Prosper or Allen?

Before the drawings go to the city and to the accessibility reviewer, they should show the network closet and its power and cooling, the dedicated circuits for the server and imaging equipment, and the front-desk and check-in hardware where it will really sit. Anything added after review becomes a revision. Revisions take time, and time is the one thing a finish-out schedule does not have.

The cable runs themselves usually live on the low-voltage contractor's drawing rather than the architect's set. What the architect's set does carry is everything that affects walls, power, ceilings and accessibility: the closet room, its door and ventilation, the electrical circuits behind each piece of equipment, backing in walls and ceilings for screens, and the counter where the front desk works. For a dental office, those are the items that decide whether the network can be built as planned.

A short list to take to the drawing review with your architect:

    • The closet. Which room, how big, which wall the rack sits on, and how heat leaves the room. A closet that shares a wall with a restroom or a water heater is a question to raise now, not at rough-in.
    • The circuits. A dedicated circuit for the rack, and circuits where imaging equipment, a panoramic or cone-beam unit and the main printers will sit.
    • The front desk. Where each check-in computer, payment terminal, label printer and patient-facing screen goes, drawn at the size it really is.
    • Backing. Wall and ceiling backing for operatory screens, waiting-room screens and any camera mounts.
    • The entry point. Where the building's telecom service enters the suite, and how it reaches the closet.

If the suite is a second-generation space, add one item: the existing closet, marked as kept, moved or removed. A closet moved on paper after review is a revision. A closet moved in the field without a revision is a problem at the final inspection.

Gate 3: When does cable have to be finished before the above-ceiling inspection in a Frisco or Prosper build?

Data, camera and AV cable has to be pulled, labelled and tested before the inspection that covers the space above the ceiling. Once that inspection passes, the ceiling closes, and a cable added later means lifting tiles or opening finished work. Ask the city's building inspections office which inspections your finish-out needs, and book the ceiling inspection only after the low-voltage cable is in.

Cities in Collin County each run their own building inspections office, publish their own inspection guidance and change it from time to time. We could not open the Frisco or Prosper inspection pages at their source on 28 November 2026, so this guide does not quote either city's process. Legend's other Dallas–Fort Worth guides do not state a city permit rule for low-voltage cabling, and neither does this one. The city is the authority on its own rules, and your GC is the person who reads them for your project.

The question for the city or your GC. "Which inspections does this finish-out need, what does each one cover, and on which inspection is the space above the ceiling checked and closed?"

What the IT side controls is the date its own work is finished. One Collin County build shows the order plainly. Turtle Bay Pediatric Dentistry in Sachse is described on its project page this way:

> "Legend's September 2025 post shows its team on site wiring the new Turtle Bay Pediatric Dentistry office in Sachse, Texas. The wiring allowed the in-wall inspection to be scheduled."

That second sentence is the whole point of this gate. The wiring came first, and the inspection could only be booked once it was in. Swap the order and one of two things happens: the inspection slips while cable is pulled, or the inspection passes and cable is pulled through a closed ceiling later.

Three habits keep the cable ahead of the inspection:

    1. Get the date in writing. Ask the GC to send the planned ceiling inspection date to the IT provider and the low-voltage contractor the day it is booked, and again each time it moves.
    1. Pull everything, including later rooms. Cable for a future operatory, a later camera position or a second patient screen costs least while the ceiling is open. The device can wait; the cable cannot.
    1. Test before the inspection, not after. A labelled, tested run is a finished run. An untested run is a guess that the ceiling will hide.

The inspection-gate calendar: what must IT have done before each gate?

Each gate in a finish-out has a technology task that must be finished before it. Before the lease, the IT provider has seen the suite. Before review, the drawings carry the closet and circuits. Before the ceiling inspection, the cable is in and tested. Before the final inspection, the equipment is installed and tested. Before the RAS inspection, nothing has moved from the drawings.

Table C. The inspection-gate calendar

GateWhat IT must have done before itWho owns the gate
Letter of intent / lease signedFloor plan reviewed; device list drafted per room; for a second-generation suite, the existing closet seen and inherited cable test plannedPractice, broker
Drawings and TDLR registration (if $50,000 or more)Closet location, its power and cooling, dedicated circuits and front-desk hardware placement on the drawingsArchitect
Building permit issuedInternet circuit ordered; low-voltage contractor engaged; cable drawing in progressGC (permit), practice (circuit order)
Rough-inCable paths agreed with the electrician and the mechanical trade; closet backboard and power in placeGC, electrician, low-voltage contractor
Above-ceiling / ceiling cover inspectionData, camera and AV runs pulled, labelled and tested, including runs for later rooms; inherited cable in a second-generation suite testedGC books it; low-voltage contractor and IT provider finish before it
Final inspection and certificate of occupancyRack built; firewall, switches and Wi-Fi up; workstations, imaging and phones installed and tested; equipment staged earlier, installed only once the space is cleanGC books it; IT provider finishes before it
RAS inspectionNothing at the front desk or check-in point moved from the drawings; any move cleared with the architect firstArchitect advises on timing

Two rows deserve a note. The internet circuit sits at the permit row because the carrier's work runs on its own calendar and is often the last item to arrive. Why that matters more north of US 380, where streets and utilities are still being built, is covered in our guide to dental office internet in Prosper. And the equipment row says "staged earlier, installed only once the space is clean": computers and imaging units installed while drywall dust is still in the air are a common early failure.

If you would like someone to lay your own construction schedule against this calendar before the lease is signed, a Free Dental IT Assessment is a simple way to get that second look.

Gate 4: What must not move between the final inspection, the certificate of occupancy and the RAS inspection?

Ask your architect where the accessibility inspection falls in your own schedule. Until it is done, keep the front desk, the check-in point and any patient-facing equipment exactly where the drawings put them. A late move by the IT side can turn into a question at that inspection.

What the rule text says. Both public TDLR records in the worked example carry the same note, citing 16 Texas Administrative Code §68.52: "the owner of a building or facility must obtain an inspection from a RAS no later than the first anniversary of the completion of construction." It adds that the request for inspection "must be made by submitting a written request for inspection to the RAS no later than 30 calendar days after the completion of construction."

The question for your architect. "When will the RAS inspection be requested, who sends the request, and what at the front desk must stay exactly as drawn until then?"

For the IT side, this gate is about restraint. The opening weeks are when staff ask for small changes: a second monitor on the check-in counter, a tablet stand by the door, a printer moved to the end of the desk. Each request is reasonable. Each is also a change to equipment the reviewer saw on the drawings. A simple rule works: any move of front-desk, check-in or patient-facing equipment before the RAS inspection goes to the architect first. Everything behind the scenes, such as the closet, the servers and operatory computers that stay in their drawn positions, can be tuned freely.

Which gate did each Collin County build have to meet?

Real Collin County openings show the gates in action. Each project page below is quoted exactly as it is published on Legend's site, followed by one line on the gate it illustrates. The pattern is consistent: the network infrastructure was finished early, and the opening date was fixed long before the last device was installed.

Hunt Family Dentistry in Frisco

> "Legend’s posts from December 2023 to February 2024 follow Hunt Family Dentistry in Frisco, Texas, from completed network infrastructure to opening day."

The gate it illustrates: the network infrastructure was complete before the final push to opening, which is the order the ceiling and final inspections require.

Koelker Dental in Allen

> "Legend’s May 2026 post covers the technology work at Koelker Dental, Dr. Kris Koelker’s new dental startup in Allen, Texas. It lists network infrastructure, servers, security cameras, audio and video, and rack builds, with a June 30 grand opening."

The gate it illustrates: cameras, audio and video and rack builds all had to land before a grand-opening date that was already public, so every cable for them had to be in before the ceiling closed.

Dayglow Dentistry in Allen

> "Legend’s posts from January to May 2024 follow Dayglow Dentistry in Allen, Texas, from the construction-site buildout and technology installation to the grand opening."

The gate it illustrates: technology work that starts on a construction site runs through every gate in Table C, from rough-in to the final inspection.

Other Collin County builds on Legend's project pages follow the same path. Panther Creek Dental in Frisco was worked on from the slab pour to opening day, according to its March 2023 page. Flourish Dental Boutique in Frisco shows low-voltage cabling being installed at its second location in July 2026, with the location announced as coming soon that September.

If you practise in the south of the county and are weighing a move into a newer building, the same gates apply; the page on dental IT support in Allen explains how support is arranged once the doors open. For practices on the Denton County side of the Tollway, the companion guide on dental IT support in Lewisville covers that county's own utilities and openings.

Who installs the cameras and door access, and what should you ask before the ceiling closes?

Cameras and door access are often installed by a different company from the one that pulls the data cable, and their cable has to meet the same ceiling inspection. Before that company starts, find out who they are, which licence covers their work, who will own the recorder and its admin login, and where their equipment will sit in the closet.

Koelker Dental's scope above lists security cameras, and many Collin County builds add cameras and door access during the finish-out. Licensing for security work in Texas is set by the state, and this guide does not describe it. Ask the installer directly, and ask your GC to check the answer.

Questions to ask the camera and door-access installer before rough-in:

    • Which Texas licence, if any, covers your camera and door-access work, and what is the number?
    • Are your camera runs on the cable drawing, and will they be pulled before the ceiling inspection?
    • Where will the recorder sit, and does it need space and power in our network closet?
    • Who will hold the recorder's admin login and the door-access system's admin account at handover? (The answer should be the practice.)
    • How long is footage kept by default, and who sets that number?
    • Will the cameras sit on their own network, separate from the clinical computers?

For how cameras and door access fit a dental office's network, see our guide to dental office security cameras and access control.

What should the GC, the low-voltage contractor and the IT provider agree in writing about the inspection schedule?

Agree in writing who books each inspection, the last day a cable can be added before the ceiling inspection, who pulls, tests and labels every run, who orders the internet circuit, and who tells the IT provider when the schedule moves. Without those answers on paper, the technology work drifts behind the inspections that are supposed to set its dates.

Checklist D. Questions for the GC and the city

    1. Which inspections does this finish-out need, and who books each one?
    1. Is the project registered with TDLR, and when will the RAS inspection be requested?
    1. What is the last day a data, camera or AV cable can be added before the ceiling inspection?
    1. Who pulls the data, camera and AV cable: the low-voltage contractor, the camera installer or someone else?
    1. Who tests and labels each run, and who receives the test results?
    1. Where is the closet, and what power and cooling does it get on the drawings?
    1. Who orders the internet circuit, and on what date?
    1. Who holds the inspection schedule, and how is the IT provider told when it moves?
    1. What happens to a run that is added after the ceiling is covered, and who pays for it?
    1. Who owns every account, recorder and admin login at handover?

Everything else in opening an office, from the first drawing to the first patient, is covered in our new dental office IT setup, step by step guide. Checklist D stays with the inspection schedule, which that guide leaves to your GC and your city.

On cost, plan for the technology in two parts. Legend's ongoing support is published as "Starting at $360 per month". Hardware procurement, major cabling projects and software licensing are quoted separately, and startups are custom quoted, because two finish-outs as different as the filings above do not share a price. For how Legend works on dental startup IT across Dallas–Fort Worth, and the build-outs service behind it, those pages carry the detail.

How do you choose an IT provider for a Collin County finish-out?

Choose a provider that asks for your floor plan and your construction schedule before it quotes, works to the GC's inspection dates, and leaves every account in the practice's name. For a finish-out, the real test of a provider is whether its own work is finished before the ceiling inspection.

Our guide to the best dental IT companies sets out how to compare providers more widely. For a finish-out, add the gate test: ask each provider which gate in Table C its own work must beat, and listen for whether the answer is specific. A Free Dental IT Assessment from Legend starts from the same two documents: your floor plan and your construction schedule.

On Legend's side, the facts are these. Legend has served over 3,500 practices since 2004 and has 22+ years in dental IT (since 2004). It is headquartered in Dallas and has in-house engineers; no outsourced first-level triage. Onsite dispatch is by appointment across served dental markets; remote-first nationwide. Day-to-day software and support issues are handled remotely; cabling, installations, equipment moves and new-office build-outs are scheduled onsite by appointment. The helpdesk is staffed 24/7 at 1-800-794-1588. Legend's reviews stand at 4.8 rating · 173 Google reviews. Ian Lynch, 22 years in dental IT, oversees the NOC, onsite dispatch and client technology roadmaps. For the wider picture of how Legend handles dental IT support, that page is the place to start.

What to ask your IT provider before the first inspection

  • At which stage do you want our floor plan, and what will you mark up on it?
  • Which date do you need from the GC for the ceiling inspection, and how much notice do you need if it moves?
  • Who will be on site for the cable test, and in what form will we receive the results?
  • When should we order the internet circuit, and who will meet the carrier?
  • What do you need from the camera and AV installers, and by when?
  • For a second-generation suite: which inherited runs will you test, and before which gate?
  • Which front-desk and check-in equipment is on the drawings, and how will you keep it where it is drawn?
  • What do we own at handover: which accounts, which admin logins, which recorder?

Key takeaways

    • In a Collin County finish-out, the inspections set the technology dates. Data, camera and AV cable must be pulled, labelled and tested before the ceiling inspection.
    • Plan for the state gate: at an estimated $50,000 or more, the finish-out goes on TDLR's registry, and an accessibility specialist reviews the drawings and later inspects the suite. The architect files.
    • Two public Frisco dental filings estimate $190,000 and $221,000 and list durations of about 23 and 61 weeks. Neither scope line mentions data cabling.
    • A cold shell gives you control of every run; a second-generation suite saves time only if its old cable passes a test before your own inspections.
    • Keep front-desk and check-in equipment where the drawings put it until the RAS inspection is done.

Sources

    • Texas Department of Licensing and Regulation, Architectural Barriers FAQ (registration and review for projects of $50,000 or more), opened 28 November 2026.
    • Texas Department of Licensing and Regulation, TABS public project records for two Frisco dental finish-outs (registered March 2025 and October 2025), opened 28 November 2026; the RAS inspection note on each record cites 16 Texas Administrative Code §68.52.
    • U.S. Census Bureau, city and town population estimates for July 2024 to July 2025 (Vintage 2025), news release dated May 14, 2026.
    • Legend Networking project pages for Hunt Family Dentistry, Koelker Dental, Dayglow Dentistry, Turtle Bay Pediatric Dentistry, Panther Creek Dental, Prosper Star Dental Co. and Flourish Dental Boutique.
Questions

Frequently asked questions

Is a cold shell or a second-generation dental suite simpler for the technology?

A cold shell is simpler to plan, because you decide every cable route, the closet and the circuit entry before the drawings are made. A second-generation suite can be quicker, but only if the inherited cable and closet pass a test before your own permit and inspection dates. The more you re-plan an old suite, the more it behaves like a cold shell, and the same gates apply.

Does a dental finish-out in Texas need to be registered with TDLR?

Yes, once the total estimated cost reaches $50,000. Projects at that level are registered with TDLR and reviewed and inspected by a Registered Accessibility Specialist. Your architect handles the filing; the IT question is what has to be in place before each inspection. Ask the architect whether your project is registered, who the specialist is, and which drawing set they reviewed.

When does the data cabling have to be finished in a Frisco or Prosper build?

Before the inspection that covers the space above the ceiling. Once that inspection passes, the ceiling closes, and cable added later means lifting tiles or opening finished work. Ask the city's building inspections office which inspections your finish-out needs, have the GC send you the ceiling inspection date, and pull, label and test every data, camera and AV run the week before it.

What happens if network cable is not in before the above-ceiling inspection?

One of two things. Either the inspection is pushed back while the cable is pulled, which can delay every later gate, or the inspection passes and the cable is pulled through a closed ceiling afterwards, which costs time and can damage finished work. Either way the opening date is at risk. Getting the inspection date in writing and testing cable before it avoids both.

Who requests inspections, and how does the IT schedule follow them?

On most commercial finish-outs the general contractor requests the city inspections through the city's own process, and your architect can tell you who requests the accessibility inspection. The IT provider does not book them. It plans its own work to their dates, so ask the GC to send each inspection date to the IT provider and the low-voltage contractor when it is booked and whenever it moves.

What should be tested first in a second-generation suite in Plano or Frisco?

Test every inherited data cable run and look at the existing closet before the first inspection that would cover the ceiling. A run that fails a test while the ceiling is open is easy to replace; the same run found after the ceiling inspection is not. Plan the test at the letter-of-intent stage, and do not count on old cable in your schedule until it has passed.

How long does a dental finish-out take in Collin County?

Timelines vary with the building, the contractor and the city. Two public TDLR filings for Frisco dental finish-outs list about 23 weeks for a 1,886-square-foot suite and about 61 weeks for a 3,400-square-foot renovation, from listed start to listed completion. Those are estimates entered on a form, not predictions. Ask your GC for your own schedule and the ceiling inspection week.

What should the general contractor and the IT provider agree in writing?

Agree who books each inspection, the last day a cable can be added before the ceiling inspection, who pulls, tests and labels each run, where the closet is and what power and cooling it gets, who orders the internet circuit and when, how schedule changes reach the IT provider, who pays for a run added after cover, and who owns every account and recorder at handover.

The bottom line

Whichever suite you choose, the technology dates are easier to set with the floor plan and the inspection schedule in front of someone who reviews dental offices. Ask for a Free Dental IT Assessment, and bring the floor plan and the inspection schedule, whether you are leasing a cold shell in Prosper, re-planning a second-generation suite in Plano or finishing out a new building in Frisco. For the wider picture, see how Legend handles dental IT support across every stage of a practice.

Ian Lynch
About the author

Ian Lynch

Owner & Operator, Legend Networking

22 years in dental IT. Oversees the NOC, onsite dispatch and client technology roadmaps for practices nationwide.

  • Operations center

    Dallas, Texas

    Serving dental practices nationwide since 2004

  • NOC hours

    24/7 monitoring

    Helpdesk staffed 24/7 at 1-800-794-1588

  • Engineers

    In-house only

    No outsourced first-level dental IT triage

  • Onsite dispatch

    By appointment

    Technicians deployed across served dental markets

About Legend Networking
Your next step

Plan your finish-out with a Free Dental IT Assessment

Tell us what you are running and we will review it with you.

Or call 1-800-794-1588