Opening Where the Roads Are Still Being Built: Power and Internet for Dental Offices in Celina and Prosper
Picture an example: a new office in Celina or Prosper, eight months open, the morning schedule full. At 9:10 the lights blink. At 9:40 they blink again. Just before lunch a crew trenching the frontage road across the street goes through a line, and the phones and the cloud schedule go quiet together.
Legend's service for Collin County offices sits under dental IT support in Dallas–Fort Worth, which covers the whole metro. This guide covers power and internet for a new dental office in Celina and the towns around it while they are still being built: a short-outage rule for a clinic day, a site check of the construction around your pad, and a table of what an opening is blocked by if power or internet arrives late. For the rest of the county, from the built-out south to the tollway corridor, see the guide to dental practice IT in Plano, Frisco and McKinney.
Four things to take from this guide:
- The risk in a fast-growing town comes from construction around the site: lines being rebuilt, roads widened, pads trenched. Storms are a separate plan.
- Repeated short outages and surges are harder on computers and open charts than one clean outage. A written rule for the second and third flicker protects more data than any device.
- Two internet connections can still fail together if they share a trench, a pole line or a street. Ask each carrier how the line reaches the building.
- When construction holds up power or the line, an opening can still move ahead on cabling, accounts and local testing. Decide in advance what waits and what a cellular line carries.
North of US 380, expect many short interruptions more often than one long blackout. Power lines are being rebuilt for growth, and road crews dig where your internet runs. Plan for short outages and surges, bring internet in on two routes that do not share a trench, and order the circuit when you sign.
- The risk in a fast-growing town comes from construction around the site: lines being rebuilt, roads widened, pads trenched. Storms are a separate plan.
- Repeated short outages and surges are harder on computers and open charts than one clean outage. A written rule for the second and third flicker protects more data than any device.
- Two internet connections can still fail together if they share a trench, a pole line or a street. Ask each carrier how the line reaches the building.
- When construction holds up power or the line, an opening can still move ahead on cabling, accounts and local testing. Decide in advance what waits and what a cellular line carries.
In this guide
- Why do offices in Celina, Prosper and Anna face different power and internet risks from established suburbs?
- What happened in Celina in April 2026, and what does it teach a dental office?
- What should a dental office do when the lights flicker several times in a morning?
- How can road or utility construction near your suite take the internet down?
- What is being built near your pad, and why should you know before opening?
- What can an opening in Anna, Melissa or Princeton still do if construction holds up power or the internet line?
- Is your office on Oncor's wires or a cooperative's, and does it change the plan?
- What did practices that opened north of US 380 have to get right?
- Which changes around the site should send you back to the plan while the area is still being built?
- What to ask your IT provider about power and internet in a growing town
- Frequently asked questions
- The bottom line
Why do offices in Celina, Prosper and Anna face different power and internet risks from established suburbs?
An office in a built-out suburb sits on lines and streets that were finished years ago. North of US 380 the grid, the roads and the neighbouring pads are still under construction, so the everyday risks are planned and unplanned interruptions from that work: a line being rebuilt, a road crew digging, a carrier still building to a new pad.
The scale of the growth is a matter of public record. In its Vintage 2025 estimates released on May 14, 2026, the U.S. Census Bureau ranked Celina the fastest-growing city of 20,000 or more people in the country, up 24.6% to 64,427 between July 2024 and July 2025. Princeton was third at 18.1%, Melissa fourth at 14.5% and Anna fifth at 10.2%. All four are in Collin County.
Roads follow people. The North Texas Tollway Authority is extending the Dallas North Tollway north of US 380 through Prosper and Celina. As of November 2026, NTTA lists Phase 4A, from US 380 to FM 428, with an opening target of late 2027, and Phase 4B to the Grayson County line as "to be determined". The bridges carrying the tollway over US 380 into Prosper opened in 2023. Around the mainlanes come new frontage roads, widened county roads, turn lanes into new retail centers and the water, sewer and power lines that serve each new subdivision.
None of this is bad news for a practice. Growth is why owners open here. It does change three parts of the technology plan:
- Power. Utilities rebuild lines in stages to carry new load. Expect switching, planned work and more frequent short interruptions while that happens, and plan for the second and third flicker in a morning.
- Internet. Every new road and pad means digging. The line feeding your suite may cross ground that someone else will open next month.
- Timing. A new pad may have no carrier service yet. The circuit can be the longest-lead item in the whole opening.
Storms are a separate question. For hail, ice and metro-wide grid emergencies, and the copies an office should keep before them, see Legend's page on dental backup and disaster recovery across Dallas–Fort Worth. This guide stays with the construction going on around the site.
What happened in Celina in April 2026, and what does it teach a dental office?
On April 7, 2026, NBC DFW reported that businesses in downtown Celina were dealing with power outages that had become more frequent and were lasting longer, one of them nearly 12 hours. Oncor said it was running a multiphase reliability improvement project in Celina, accelerated because of the outages and the city's growth.
According to the city, the upgrades include more than 100 new poles, about 400 replaced crossarms and advanced circuit switches. Oncor also said the most recent outage in that report had been caused by severe weather. The report described restaurants and shops throwing away stock after the outages. Those businesses are not named here, and nothing in this guide predicts how often outages will happen in any part of Celina.
Three lessons carry over to a dental office:
- A rebuild is good news with interruptions attached. New poles, crossarms and switches are how a utility makes a growing town's lines stronger. The work itself can bring planned outages, and switching load between circuits can bring short ones.
- Repeated drops do more harm than one clean outage. A practice that loses power once at 2 p.m. shuts down and waits. A practice that loses power for a few seconds three times in a morning can have charts open, imaging mid-capture and computers that restart half-way through updates each time. Every unsaved note and every interrupted write to the database is a small risk, and they add up.
- The cost of an outage is the schedule. A restaurant loses stock. A dental office loses appointments it has to call and rebook, plus the time spent checking that every system came back properly. That is why the rule in the next section is about people and timing more than equipment.
What should a dental office do when the lights flicker several times in a morning?
Follow a written rule that changes with each flicker. At the first, staff save and close what is open. At the second within the hour, the front desk protects the rest of the day's schedule. If the power goes out, battery-backed core equipment holds while everything else shuts down, and nobody restarts until power has been stable for the period your IT provider sets.
The rule works because it removes decisions from a busy morning. Post a printed copy at reception and in sterilisation, and make it part of every new hire's first-week training.
Rule A: the short-outage rule for a clinic day
| What happens | Front desk | Operatories and imaging | Do not |
|---|---|---|---|
| First flicker | Save and close any open patient record and the ledger. Note the time on the outage log. | Clinicians save notes and close charts at a natural pause. Pause any imaging capture until the lights have held. | Restart a computer that stayed on. Touch the server, the firewall or the network closet. |
| Second flicker within the hour | Print or export the rest of the day's schedule with phone numbers, so the day can run on paper if needed. Tell the office manager. | The doctor decides whether to keep capturing images or move to procedures that do not need a capture until the lights settle. | Start a large upload, a software update or a scanner sync. |
| Power goes out | Battery-backed devices keep running: in most offices the server, firewall, internet modem, main switch and one front-desk computer. Shut down every other computer from the operating system. | Shut down operatory computers and imaging workstations normally if they are not on battery. Leave sensors and scanners unplugged from charging until power returns. | Switch anything back on at the first sign of power. |
| Power comes back | Wait until power has been stable for the period your IT provider gave you. Write that number on this sheet. | Stay shut down until the front desk says the wait is over. | Log in before the IT provider confirms the server and backups are healthy. |
| Third flicker, or a pattern over several days | Call your IT provider and log the times. If your utility offers outage alerts, check whether they match. | Carry on under the second-flicker rule for the rest of the day. | Assume it will stop on its own. A pattern is information for your provider and the utility. |
This guide does not give a waiting period, because the right one depends on your equipment and on what your provider is monitoring. The point is to agree a number in advance so the front desk is not guessing at 10 a.m. with a full waiting room. If you want to understand why a proper restart and a quick off-and-on are not the same thing, read Legend's explainer on whether to restart or power cycle office equipment.
Worked example (illustrative numbers). A 5-operatory office in Prosper has seven workstations in use on a typical morning: five chairside computers and two at the front desk. Three short flickers before noon, with no rule, means up to 21 moments when an open chart, a ledger entry or an imaging session is interrupted mid-write. With Rule A, the first flicker closes the open charts, so the second and third flickers find little to damage. The front desk printed the afternoon's schedule after the second, so when the line also dropped at 11:50 the team could still call patients from the printout. Nobody needed a new device to get that result. They needed a sheet and ten minutes of training.
How can road or utility construction near your suite take the internet down?
When a crew digs, bores or replaces poles along a street, it can cut the fiber, cable or copper that carries your internet. Two connections from two carriers can still fail together if both reach the building through the same trench, pole line or street. The protection is a second route that physically enters from somewhere else.
In May 2018 a single turn-lane crew in Frisco took one carrier's phones and internet down far from the dig site, as the guide to the 2018 fiber cut across Denton County explains; that is how construction fiber cuts and dental offices connect, because the risk follows the route of your line.
North of US 380 that ground is being dug constantly. A new frontage road, a turn lane into a shopping center or a sewer main for a new subdivision can each cross the path your service takes. Nobody can stop that. You can choose how your office is connected and what it does when a line goes.
Questions to ask each carrier before you sign the order:
- Does your line to our building run along a road that is being widened, extended or given a new frontage?
- Is that stretch buried or on poles, and will the road project relocate it? If it moves, will you tell us before the work starts?
- At which wall does the line come into the building, and does it cross the driveway or the frontage on the way in?
- Which stretch, if any, shares a trench, a pole line or a street crossing with the other carrier's line?
- Does a cellular backup have a usable signal inside the room where the equipment will sit, and not only in the parking lot?
- When a third-party crew cuts the line, who reports it, and what information will you want from us?
Write the answers down, with the date and the name of the person who gave them. They are the facts your IT provider needs to design the second path. For the design itself, how the backup line is chosen, what rides on it and how failover is tested, use Legend's guide to backup internet design for a dental office; this guide does not repeat it. For the front desk's first checks once a line has dropped, keep Legend's dental office internet down checklist bookmarked.
What is being built near your pad, and why should you know before opening?
Know what construction is planned within sight of the suite, because each project can cut a line, interrupt power or delay a carrier's build. A short site check at the letter of intent, again when the circuit is ordered and monthly in the first year tells you what to ask the town and the carriers before it becomes an outage.
Most owners look at traffic, signage and parking when they choose a pad. Few look at the road crew's plans for the next eighteen months. In a town growing as fast as Celina, Prosper, Anna, Melissa or Princeton, the second list matters as much for the technology as the first.
Site check B: what's being built near your pad
| What is being built | What it can cut or interrupt | What to ask, and whom | When to re-check |
|---|---|---|---|
| Tollway or highway mainlane work in sight of the suite | Fiber and copper along the corridor; pole lines moved for the new road | The town's public works or engineering page, and NTTA or TxDOT project pages, for the work schedule near your frontage; each carrier, whether its line follows that corridor | At the letter of intent; at circuit order |
| Road widening or new turn lanes on your frontage | The line entering your building, if it crosses the frontage; power poles moved | The town's engineering department about planned work on your street; the carrier about how deep and where the line crosses | At circuit order; monthly in year one |
| New subdivisions or retail pads being trenched next door | Lines in a shared easement; temporary power cuts when a new transformer is set | The landlord or developer about later phases of the center; the town's development page for approved plans | Monthly in year one |
| Utility pole or line work on your street | Short planned outages and switching; overhead fiber moved with the poles | Your electricity provider's planned-outage notices; the carrier, whether its line is on those poles | When notices arrive; before any planned outage |
| Water or sewer work in the right-of-way | Lines cut by boring or trenching | The town's public works notices; the landlord, about any work on the property | At the letter of intent; when notices arrive |
| Later phases of your own center | Shared conduit reopened; power or carrier work in the building's utility room | The landlord, about the build schedule for the rest of the center and who controls the utility room | Before opening; at each new phase |
Three rules keep the check honest. First, check with the town for every specific: a project page or a call to engineering beats a guess from the road. Second, keep the carrier's repair number at the front desk, next to the utility's outage line printed on your bill, so whoever is on shift can report a cut without searching. Third, record what you learn with a date. A note that says "frontage widening planned, carrier line crosses at the driveway, asked 3 March" is worth far more than a memory.
If you would like a second pair of eyes on the site, the carrier answers and your plan for the first year, Legend offers a Free Dental IT Assessment for practices opening or settling in north of US 380.
What can an opening in Anna, Melissa or Princeton still do if construction holds up power or the internet line?
Quite a lot, if the order of work was planned. Cabling, accounts, training and local testing can go ahead without permanent power or a live line. What waits is anything that needs the closet powered or the internet up. Table C shows which tasks wait, which proceed and what to decide before a delay arrives.
North of US 380 the delays that touch the technology usually come from the work around the site, not from inside the suite. A transformer for a new phase of the center has not been set yet. A carrier crew is waiting for a road project to finish before it can cross the frontage. A lane closure moves an install visit by a week. None of these sits in your contract or your IT provider's, and none comes with a date anyone can promise, so this guide gives no lead times. Ask each party for its date in writing and treat it as a forecast.
Where the circuit, the data cabling and the network closet have to be ready inside the finish-out's inspection gates is set out in the inspection calendar for a new dental office. Use that calendar for the sequence and the table below for the day a piece of it slips.
Table C: the opening-day dependency table
| If this is late | What is blocked | What can still go ahead | Decide in advance |
|---|---|---|---|
| Permanent power to the suite | Powering up and testing the network closet; server set-up; imaging workstation and sensor calibration; phone handsets; door access and cameras | Cable runs and labelling; account set-up for software and email; staff training on loaner devices off-site | Who confirms the power date with the general contractor, and what gets tested first on the day it arrives |
| The main internet line | Go-live of cloud practice software and electronic claims; testing card terminals and internet phones on site; remote set-up by the IT provider; the first offsite backup | Local network testing; imaging on the local network; printer and scanner set-up; paper or exported schedules for the first days | Whether a cellular line will carry the opening, and for which systems |
| Only a cellular line is live | Large image uploads; software and system updates; streaming or patient Wi-Fi | Front-desk scheduling and claims, card payments and the phones, if the cellular line was set up and tested for them | Which devices are allowed on the cellular line, and who switches the rest on when the main line arrives |
| The second internet route | Nothing on day one, if the main line is live; the office simply runs without its backup | Opening on schedule, with a written date for the second route | Who chases the second route after opening, so it does not slip for months |
The last row is the one that slips most often. Once the office is open and busy, a missing backup line stops feeling urgent. Put a name and a date beside it before the opening.
Two habits help when the hold-up comes from the road. Ask the carrier which project it is waiting on, then look that project up on the town's or NTTA's page, so the opening plan follows the road schedule instead of a guess. And re-run Site check B for that project, because the crew that delayed your line before opening is often the one digging beside it afterwards.
Is your office on Oncor's wires or a cooperative's, and does it change the plan?
Check the electricity bill. Many offices in the core suburbs are on Oncor's wires, with electricity bought from a retail provider, while CoServ and Grayson-Collin Electric Cooperative serve parts of the area. What changes is the outage number on the front-desk sheet and the utility you report a pattern of flickers to.
CoServ is an electric cooperative headquartered in Corinth, with service centers that include Prosper and McKinney. Grayson-Collin Electric Cooperative serves parts of Grayson and Collin counties. In practice, the organisation that owns the wires to your suite is the one that restores them and the one that sends outage updates.
You cannot tell which applies from the town name or the ZIP code, so do not assume. Look at the bill or ask the landlord for a recent one before you sign. Then write three things on the front-desk copy of Rule A: the utility's name, the outage line printed on the bill and the account number. The person who logs the third flicker can then report the pattern without searching for a number.
That is the whole change to the plan. Rule A, the site check and the dependency table work the same way on either system. The wider county picture, including the built-out south, is in the county guide linked at the top of this page.
What did practices that opened north of US 380 have to get right?
Every practice that opens in a town still under construction has the same short list: the technology finished before the first patient, the security systems working on day one, and a long run from announcement to opening that the circuit and the cabling have to fit inside. Legend's live project pages include three such openings in Celina and Prosper.
> "Legend's September 2025 post marks the opening of Marengo Pediatric Dentistry in Celina, Texas, led by Dr. Shireen Khan."
Marengo Pediatric Dentistry in Celina opened in the city the Census Bureau would rank the fastest-growing in the country the following spring, which is the setting this guide is written for.
> "Legend's October 2024 post congratulates Prosper Periodontics & Dental Implants in Prosper, Texas, on its new practice. Legend was in the final stages of building out its technology and security systems with Dr. Praveen Parachuru."
At Prosper Periodontics & Dental Implants, the final stage before opening was the technology and security systems, the same items that sit on the power and internet rows of Table C.
> "Legend’s August and November 2023 posts cover Buchwald Orthodontics in Prosper: the announcement that Legend is working with Dr. Bradley Buchwald on his upcoming practice, and a progress update with buildout photos."
Buchwald Orthodontics in Prosper shows the span from announcement to buildout, which is the window in which a circuit should be ordered and a site check repeated.
None of these pages describes an outage, a fiber cut or a recovery, and this guide does not suggest one. They show openings in the towns this guide covers. Practices south of US 380, in McKinney or Allen, will find how Legend covers that side of the county on the page for dental IT support in McKinney.
Which changes around the site should send you back to the plan while the area is still being built?
Review on a calendar and on events. Re-read Site check B and the outage log monthly in the first year, and again whenever something around the site changes: a new phase of the center breaks ground, a road project starts or finishes on your frontage, the utility posts planned work, or a second carrier reaches your street.
In a built-out suburb the plan written at opening can sit in a drawer for years. North of US 380 the ground around the suite keeps changing, and some of those changes are good news: a finished rebuild can mean fewer flickers, and a new carrier on the street can make a second route possible that was not on offer at opening. The table below turns those events into a short update.
Table D: construction triggers and what to update
| What changes near the site | What it can change for the office | What to update |
|---|---|---|
| A new phase of your center breaks ground | Shared conduit or the utility room reopened; temporary power cuts | Site check B, last row; give the dates to your IT provider |
| A road project starts or finishes on your frontage | The route of your line; a new crossing; poles moved | The carrier's route answers, dated again |
| The utility posts planned work on your street, or finishes a rebuild | Planned outages during the work; fewer short ones after it | Compare the outage log before and after; keep Rule A posted either way |
| A second carrier builds along your street | A physically separate route becomes possible | Ask where its line would enter; put a date in Table C's last row |
| Three or more flickers in a week | A local line problem or worn equipment | Log the times, call your IT provider, report the pattern to the utility |
| A new front-desk hire | Rule A known by fewer people | Train the rule in the new hire's first week |
When a trigger calls for a network change, such as a new entry point for a second line or moving where a line lands in the suite, Legend's network design service covers that work. Owners still choosing who will hold the systems side can read Legend's overview of dental IT support, then compare it against the best dental IT companies list before building a shortlist.
For the record, here is how Legend is set up. The company is headquartered in Dallas. There is one general number, 1-800-794-1588, with the helpdesk staffed 24/7; 24/7 monitoring is a separate service that watches the systems themselves. Legend describes its people as "In-house engineers; no outsourced first-level triage" and its delivery as "Onsite dispatch by appointment across served dental markets; remote-first nationwide." Day-to-day software and support issues are handled remotely; cabling, installations, equipment moves and new-office build-outs are scheduled onsite by appointment.
Legend has served over 3,500 practices since 2004. Its Google listing reads 4.8 rating · 173 Google reviews. The author, Ian Lynch, has "22 years in dental IT; oversees the NOC, onsite dispatch and client technology roadmaps" in Legend's published description.
What to ask your IT provider about power and internet in a growing town
Ask these before you sign the lease, and again three months after opening.
- Which devices are on battery, and which shut down when the power goes out?
- How long do you want power to be stable before we restart anything, and will you write that number on our sheet?
- How does our internet reach the building, and does the second route share any trench, pole line or street with the first?
- If a road project or the utility holds up power or the line before opening, which tasks can you still finish, and which wait?
- When a crew cuts our line, who calls the carrier, and what do you need from the front desk?
- What runs on the cellular line if the main line is down, and what stays off it?
- Which changes around the site, such as a new phase of the center or a road project on our frontage, should we tell you about?
Frequently asked questions
Why do new offices in Celina and Prosper see more short power outages than established ones?
Some new areas sit on lines that are being rebuilt for growth. In April 2026, NBC DFW reported repeated, longer outages for downtown Celina businesses, and Oncor said it was running a multiphase reliability project there, accelerated by the outages and the city's growth. Rebuilding and switching circuits can bring short interruptions. Nobody can forecast them for a given address, so plan for frequent short outages and write a rule for them.
What should a dental office do when the lights flicker several times in a morning?
At the first flicker, save and close open charts and pause imaging captures; restart nothing. At a second flicker within the hour, the front desk prints or exports the rest of the day's schedule. If the power goes out, battery-backed core equipment holds and other computers shut down normally. Restart only after power has been stable for the period your IT provider set, once the server is checked.
How can road or utility construction near our suite take the internet down?
Crews widening roads, cutting turn lanes or trenching new pads can sever the fiber, cable or copper that carries your service, even miles away. Two connections can also fail together when both lines share a trench or pole line, so a second route has to be physically separate from the first. Ask each carrier which route your line takes and whether a second line can enter the building another way.
What does "two internet paths" mean for an office north of US 380?
It means two connections that reach the building by different physical routes, so one road crew cannot cut both. Two carriers on the same pole line or in the same trench are one path in practice. Ask each carrier how its line enters the building and whether a second line can come from another side. Legend's backup internet guide covers choosing and testing the second line.
How often should the site check be repeated once the office is open?
Monthly in the first year, and again whenever something changes around the site: a new phase of the center breaks ground, a road project starts or finishes on the frontage, the utility posts planned work, or a second carrier reaches the street. Each of these can move a line, cause planned outages or make a separate second route possible. Date every update.
Which work being built near our pad should we know about before opening?
Look for tollway or highway work in sight of the suite, road widening or turn lanes on your frontage, new subdivisions or retail pads being trenched next door, pole and line work on your street, water or sewer work in the right-of-way and later phases of your own center. Check each with the town, the landlord and the carrier, and re-check monthly in the first year.
Should a practice delay opening because the utility is rebuilding lines in the area?
Usually not. A rebuild like the one Oncor described in Celina in April 2026 is how a utility strengthens lines for growth, and nobody can forecast outages at a given address. Open on schedule with Rule A posted, the battery list confirmed, the carrier route answers in writing and a date for the second internet route.
What should be on battery in an office where outages are frequent but short?
In most dental offices: the server, the firewall, the internet modem or router, the main network switch, the phone system's core equipment and one front-desk computer. Operatory computers and imaging workstations usually shut down normally instead. Have an installer size and test the units, and ask your IT provider to confirm the list, because the right devices depend on how your office is set up.
What opening-day tasks are blocked if power or internet is late?
Without permanent power, the network closet, server, imaging calibration, phones, cameras and door access cannot be tested. Without the main internet line, cloud practice software, electronic claims, internet phones, some card terminals, remote support and offsite backup copies wait. A tested cellular line can carry scheduling, payments and phones for a few days. Decide in advance which systems it carries and who switches the rest on.
The bottom line
Most of this plan costs little and takes an afternoon: a rule at the front desk, a dated site check, the carrier answers in writing and a name beside the circuit order. Opening soon, or already open, in Celina, Prosper, Anna, Melissa, Princeton or Lavon? Book a Free Dental IT Assessment and Legend will go through your outage rule, internet routes and opening dependencies with you. The wider service is described under dental IT support.