You have signed a lease on a bare shell suite in a Middle Tennessee shopping center built since 2020. Wilson County has grown about 15% since 2020 and Maury County grew 3.2% in 2025, and new centers in Murfreesboro, Mt. Juliet, Spring Hill and Gallatin can open before every carrier has built to every suite.
Ongoing support for the region is covered on Legend's page for dental IT support in Nashville. This article is the build plan for the months between a signed lease and the first patient, written for a first-time owner (often an associate stepping up; Meharry's School of Dentistry in Nashville admits a class of 75) or a group adding a ground-up location. For power companies, carriers and support across the whole region, start with our guide to dental IT in Nashville.
Start IT planning while the floor plan can still change. Order internet the week the lease is signed and get the install date in writing. Confirm which power company serves the suite. Have licensed low-voltage cabling run, labeled and terminated before the in-wall inspection, and run a readiness check before the first patient.
- In a ground-up Middle Tennessee suite, IT decisions sit inside the construction drawings: start while the floor plan can still change.
- Order internet the week the lease is signed and get the install date in writing; in August 2023 fiber was still being built in Murfreesboro.
- Middle Tennessee Electric primarily serves Rutherford, Williamson and Wilson; Cumberland EMC serves Sumner; confirm the distributor on the meter account.
- Every data drop is run, terminated, labeled at both ends and tested before the in-wall inspection, as at Building Smiles Pediatric Dentistry in Shelbyville.
- Count the build calendar back from opening day as gates: the carrier order and the in-wall inspection are the two fixed ones.
- At Legend, startups are custom quoted; hardware procurement, major cabling projects and software licensing are quoted separately.
In this guide
- Why is a ground-up suite in a new Middle Tennessee center different from taking over an existing office?
- Which Middle Tennessee growth corridor are you building in, and what changes?
- Why is the internet order the first gate in a new Murfreesboro or Mt. Juliet build?
- Who does what in a Middle Tennessee dental build?
- Who is allowed to run data cabling in a new Tennessee office?
- What has to be done before the in-wall inspection in a new Middle Tennessee suite?
- How do you count a Middle Tennessee build calendar back from opening day?
- Which power company will serve a new suite in Rutherford, Williamson, Wilson or Sumner County, and does it change the electrical plan?
- What should a first-time owner keep in their own name from day one?
- What must work before the first patient in a new Gallatin or Lebanon office?
- How is IT priced for a new dental office in Middle Tennessee?
- What to ask your IT provider
- Sources
- Frequently asked questions
- The bottom line
Why is a ground-up suite in a new Middle Tennessee center different from taking over an existing office?
A ground-up suite starts with nothing in the walls: no data cable, no network closet, no carrier line and sometimes no fiber to the building. A second-generation office comes with old cable and an old line to test. In a new Middle Tennessee center, each of those is ordered, built and inspected on the construction schedule.
That difference changes the order of work. In a take-over, IT is mostly an audit: what can stay, what must go, and how the patient data moves. In new construction, IT decisions sit inside the construction drawings. If the drawings do not show a data drop at the pano, the low-voltage crew will not run one, and adding it after drywall means cutting open a finished wall.
Growth is why so many owners here face the new-construction version. The Tennessee State Data Center counted 10,413 new Davidson County residents between July 2023 and July 2024, the most of any county, and calls Wilson the state's fastest-growing county of the decade. Retail and medical space follows the rooftops into Rutherford, Wilson, Williamson, Maury and Sumner.
Two related situations have their own guides: a group opening another location should read IT for a de novo dental office, and an owner who wants the national step-by-step setup (software, hardware, phones) should read setting up IT for a new dental practice. This article covers only what new construction in Middle Tennessee changes.
Which Middle Tennessee growth corridor are you building in, and what changes?
The county decides your likely power company and the codes office that inspects your build; the exact address decides which carriers can reach the suite. Rutherford, Williamson and Wilson are mostly Middle Tennessee Electric territory, Sumner is Cumberland EMC, and some towns run their own electric department. Carriers vary center by center.
Table A. Growth corridors at a glance (as of November 2026)
| Corridor | Towns where new suites are common | Likely power distributor (confirm on the bill) | Carrier notes | Who inspects the build | Growth fact on record |
|---|---|---|---|---|---|
| Rutherford County | Murfreesboro, Smyrna, La Vergne | Middle Tennessee Electric (MTE) primarily serves Rutherford | Fiber builds were announced in August 2023 (see the next section); check the suite address on the FCC map | The city or county codes department for the address | Check the State Data Center's county estimates |
| Wilson County | Mt. Juliet, Lebanon | MTE primarily serves Wilson; some towns run their own electric department, so check | Check the FCC National Broadband Map for the suite and ask the landlord which carriers have built to the center | The city or county codes department | +3.4% in 2024; about +15% since 2020 |
| Williamson County | Franklin, Nolensville, the Williamson side of Spring Hill | MTE primarily serves Williamson | Check the FCC map and ask the landlord which carriers have built to the center | The city or county codes department | Check the State Data Center's county estimates |
| Maury County | Spring Hill, Columbia | Depends on the address; ask the landlord and confirm on the meter account | Check the FCC map and ask the landlord which carriers have built to the center | The city or county codes department | +3.2% in 2025 |
| Sumner County | Hendersonville, Gallatin | Cumberland EMC serves Sumner; some towns run their own electric department, so check | Check the FCC map and ask the landlord which carriers have built to the center | The city or county codes department | Check the State Data Center's county estimates |
Two things in the table change your plan.
Spring Hill sits in two counties. A suite on one side of town can have a different codes office, and possibly a different power company, from a suite a few minutes away. Write the county on the cover of your project file, and use it every time you call someone.
"Fiber available" on a map is a statement about an area, not your suite. The FCC National Broadband Map is the right first check, and it is searchable by address. It still cannot tell you whether a carrier has pulled fiber into a building that was finished months ago. Only the landlord, the general contractor and the carrier's business sales team can tell you that.
Why is the internet order the first gate in a new Murfreesboro or Mt. Juliet build?
The internet order is the first gate because every other IT step waits for it, and no one on your build team controls it. A carrier may need to extend fiber into the center and run a line to your suite. Order it the week the lease is signed and get the install date in writing.
Murfreesboro shows why this matters. On 28 August 2023, United Communications, a Franklin-based provider, announced an $85 million fiber expansion to reach about 77,000 more Middle Tennessee Electric members in Murfreesboro. Three days later Google Fiber announced it was expanding to the city, with construction to follow. That is good news for new offices, and it also means carriers were still building. In a corridor where networks are being built, the carrier that serves the center next door may not yet serve yours.
The internet order is also where three common mistakes happen.
- Waiting for the walls. Owners often wait until the suite "looks like an office" before calling a carrier. By then the install date is set by the carrier's calendar, and your opening date has to fit around it.
- Accepting a verbal date. A salesperson saying "a few weeks" is not a date. Ask for the order number, the install appointment and the name of the person to call if the date moves.
- Ordering one line. The second internet line is part of the design: a different carrier on a different physical path, ordered at the same time as line one, so a cut cable or a carrier fault does not take down both. A cellular backup only counts if it rides a different carrier from your main line.
Our outage plan for a Nashville dental office explains why this region plans for power and phones failing together. For the build, ask your IT provider to confirm the two lines do not share a path into the building.
While you are on the phone with the carrier, also ask:
- Where will the demarcation point be: in your suite, or in a shared electrical or telecom room for the building?
- Will the carrier extend the line to your network closet, or stop at the demarc and leave the rest to your low-voltage contractor?
- Is there spare conduit from the building entrance to your suite, and who owns it?
- Who from your team must be on site for the install?
Write the answers in the project file. They decide one row of the next table.
Who does what in a Middle Tennessee dental build?
Seven parties touch the technology in a new dental office: the owner, general contractor, electrician, low-voltage contractor, IT provider, carrier and imaging vendor. Most delays come from tasks that sit between two of them. A responsibility table (RACI) settles who does each job, who signs off, who is asked and who is told, before a wall closes.
Table B. RACI for a new dental office build (R = does the work, A = signs off, C = consulted, I = informed, blank = not involved)
| Task | Owner / dentist | General contractor | Electrician | Low-voltage contractor | IT provider | Carrier | Imaging vendor |
|---|---|---|---|---|---|---|---|
| Device positions marked on the floor plan | A | C | I | C | R | C | |
| Electrical circuits for the network closet, battery backup and imaging | A | C | R | I | C | C | |
| Low-voltage data drops run and terminated | I | A | I | R | C | I | |
| In-wall inspection scheduled and passed | I | A | R | R | I | ||
| Carrier order, install date and demarc walk | A | C | C | R | R | ||
| Network equipment (firewall, switches, Wi-Fi access points) | A | C | R | ||||
| Phones and number porting | A | C | R | C | |||
| Practice-management software install and data | A | R | |||||
| Imaging sensors, pano and CBCT | A | C | C | C | R | ||
| Security cameras and alarm | A | C | C | R | C | ||
| Opening-week testing | A | I | I | R | I | C |
How to read it:
- The owner signs off on almost everything. That is deliberate. Accounts, contracts and the final layout should never be decided by someone who will not own the practice.
- The IT provider is "R" for positions on the drawing, not for the cable. A good IT provider marks each data drop, the closet and the access-point positions on the drawings. The licensed low-voltage contractor runs the cable. The general contractor owns the schedule that gets the inspection passed.
- The carrier and the IT provider share the demarc row. One of them should walk the building with the general contractor to agree where the line enters and how it reaches your closet.
- The imaging vendor owns the pano and CBCT install, but consults on power and cable. Ask for the vendor's site requirements in writing before the electrician prices the job. Our page on CBCT computer and network requirements lists what those documents usually cover.
- Practice-management software has its own vendor, not shown in the table; your IT provider usually coordinates the install and data with them.
If you want a provider to fill in the IT column with you and mark the drawings, Legend's build-outs and network design pages describe that work. When you are ready for an outside look at your drawings and schedule, ask for a Free Dental IT Assessment.
Who is allowed to run data cabling in a new Tennessee office?
Tennessee's Board for Licensing Contractors lists data cabling, alarms and security systems among its electrical specialties, and the right license can depend on the type and size of the job. Ask your general contractor and cabling contractor to confirm in writing which license covers your scope, and whether your codes department inspects the low-voltage work.
Here is what the state's own pages say, as opened on 24 November 2026:
- The Board's classification outline lists "Data Cable/Line" under an "Electrical / Low Voltage / Communications / Controls" heading.
- The same outline lists "Sound and intercom systems, fire detection, signal and burglar alarm systems, and security systems up to 70 volts" as its own classification (CE-D), and notes that "Separate alarm-system regulation may apply in some circumstances."
- The Board's Limited Licensed Electrician page says that license "covers work less than $25,000 per project."
We are not reading the law for you, and nothing here replaces the Board or your attorney. The practical point is that licensing has more than one layer, so three questions belong in every bid:
- Which Tennessee license does your company hold for this scope, and what is the license number?
- Does the camera or alarm work need a separate alarm contractor?
- Will the city or county codes department inspect your work as part of the in-wall inspection, and who schedules it?
Check the contractor's number on the state's license lookup before you sign, keep a copy in the project file, and ask the electrician the same questions if the low-voltage scope sits in the electrical contract.
What has to be done before the in-wall inspection in a new Middle Tennessee suite?
Before the inspector arrives, every data drop must be run, terminated, labeled at both ends and tested, with the results saved. The walls should be photographed while open, and a spare pathway left to the demarc. After drywall, a missed drop means cutting a finished wall, so this inspection is the last cheap moment to add cable.
One of Legend's own Middle Tennessee projects sits at exactly this stage. As the project page puts it: "Legend’s April 2026 post covers the cabling phase at Building Smiles Pediatric Dentistry in Shelbyville, Tennessee: low-voltage data drops run and terminated before the in-wall inspection, as groundwork for practice software, imaging, phones, Wi-Fi and security." See the Building Smiles Pediatric Dentistry project page. Drops come first, the inspection second, and everything else is built on top. Do this walk-through with your contractor first.
Checklist: before the inspector arrives
- [ ] A drop at every operatory, placed where the chairside computer and monitor will actually sit, checked against the delivery-unit position.
- [ ] Drops at the pano and CBCT positions, matched to the imaging vendor's site requirements.
- [ ] Drops at every front-desk station, including check-out.
- [ ] Drops in the doctor's office, the business or manager's office and the consult room.
- [ ] A drop in sterilization if any device there will connect (some autoclaves and tracking systems do).
- [ ] Ceiling drops for each Wi-Fi access point, positioned from a plan, not guessed.
- [ ] Drops for each camera position and the alarm panel, run by whoever holds the right license.
- [ ] Drops behind the patient TV or lobby display.
- [ ] Every cable ends in the network closet, with room for a rack, the battery backup and airflow.
- [ ] Every drop labeled at both ends with the same number, and the numbers marked on the drawing.
- [ ] Every drop tested with a cable tester, and the test results saved to the project file.
- [ ] Photos of each open wall, taken square-on with a tape measure in view, stored with the plans.
- [ ] Spare conduit or a pull string from the closet to the demarc, for the second carrier line.
- [ ] A dedicated circuit for the closet, confirmed by the electrician (see the power section).
Worked example: counting drops for a six-operatory suite in Spring Hill
Counting drops on paper before the bid keeps the quote honest and the walk-through quick. Here is the count for an illustrative six-operatory practice. Your layout will differ; the method is what to copy.
| Location | Quantity | Drops each | Drops |
|---|---|---|---|
| Operatories (chairside computer plus one spare for a second screen or a future device) | 6 | 2 | 12 |
| Pano / CBCT room | 1 | 2 | 2 |
| Front-desk stations (computer plus desk phone) | 3 | 2 | 6 |
| Doctor's office | 1 | 2 | 2 |
| Business or manager's office | 1 | 2 | 2 |
| Consult room | 1 | 1 | 1 |
| Sterilization | 1 | 1 | 1 |
| Ceiling Wi-Fi access points | 4 | 1 | 4 |
| Cameras | 4 | 1 | 4 |
| Patient TV / lobby display | 2 | 1 | 2 |
| Total | 36 |
Thirty-six drops means 72 labels and 36 saved test results. If a crew quotes for 24, you know before signing that a third of the office is missing. If you add four spare pulls to hard-to-reach places, the count becomes 40. The ratio to watch is drops per operatory: if the operatories carry only one drop each, ask why.
For the general standard behind the closet, the Wi-Fi plan and the cable itself, see our guide to dental office network setup. This section only covers the inspection gate.
How do you count a Middle Tennessee build calendar back from opening day?
Count backwards from opening day through gates, not day counts: each step can only start when the one before it is finished. The carrier order and the in-wall inspection are the two fixed gates. Everything else in the IT plan waits behind them, so a slip in either moves the opening date unless you plan for it.
Read backwards from the first patient: opening day ← readiness check ← imaging install ← workstations and practice software ← network live on the carrier line ← carrier install on a written date ← in-wall inspection passed ← drops run and tested ← device positions fixed on the drawings ← carrier ordered in lease week.
Table C. What blocks what
| Gate | Cannot start until | If it slips, it delays |
|---|---|---|
| Carrier ordered | Lease signed and suite address confirmed | The carrier install date, and every step above it |
| Device positions fixed | Imaging vendor's site requirements received | Drops, electrical pricing, the closet location |
| Drops run and tested | Positions fixed; low-voltage license confirmed | The in-wall inspection |
| In-wall inspection passed | Drops and electrical rough-in complete | Drywall; the carrier's path into the closet |
| Carrier install | Pathway to the closet finished; someone on site | Network, software, imaging and the readiness check |
| Network live | Carrier install, or a temporary connection | Workstations, phones, software |
| Imaging install | Workstations and software in place | Clinical testing and staff training |
| Readiness check | Everything above, on the real line | Opening day |
Worked example: the carrier's date lands after the imaging install
Say your opening day is a Monday. Your plan puts the imaging vendor's install on the Tuesday of the week before, with staff training on Wednesday and Thursday. The carrier's written install date comes back as the Friday before opening. What moves first?
- Push imaging, not opening day, first. Ask the imaging vendor to move the install as close to the carrier date as they can, or to do the physical install on Tuesday and leave the software connection until the line is live. Integration testing on a temporary connection proves little.
- Use a temporary cellular connection for staff training only. Staff can learn the schedule and the phones on a temporary connection. Patient data stays off it, and off the guest Wi-Fi.
- Ask the carrier for an earlier slot, in writing. Use the order number and the contact name you recorded at ordering. Your general contractor's relationship with the carrier can help.
- Protect the readiness check. If the line goes live on Friday, the readiness check runs Friday afternoon or Saturday. If it cannot run on the real line before opening, move opening day before you skip the check.
Which power company will serve a new suite in Rutherford, Williamson, Wilson or Sumner County, and does it change the electrical plan?
The name on your meter account answers it, and the county table above gives the likely company. TVA sells power to 153 local power companies, so the one that bills you depends on the address. The distributor changes your outage map and contacts, not the electrical plan: every new office needs the same few circuits.
For a new suite, confirm three things with your landlord and electrician early:
- Whose name the meter account is in. The practice's, not the developer's or the contractor's.
- Which distributor's outage map and alerts you will follow. Bookmark it and sign the office manager up for alerts.
- When permanent power is expected. The carrier install, the network and every test after it need permanent power in the suite.
The electrical plan itself does not change with the distributor. Ask the electrician to price:
- A dedicated circuit for the network closet, so the server, firewall and switches do not share power with a compressor, a vacuum or a break-room microwave.
- Circuits for the pano and CBCT to the imaging vendor's specification. The vendor's site requirements set the circuit, not the electrician's habit.
- Space and a receptacle for a battery backup (UPS) in the closet. Size it with your IT provider from the equipment list, so it can shut the server down cleanly in an outage. We do not publish runtimes; they depend on the load.
- Surge protection on the imaging equipment and the closet, matched to the vendor's guidance.
The region's outage history is why the closet circuit and the battery backup are not optional; the outage plan linked above covers what to do when power and phones fail together.
What should a first-time owner keep in their own name from day one?
Keep every account that controls the practice in the practice's or the owner's name, with the owner holding the master login: the domain, email administration, carrier accounts, practice software and imaging licenses, the firewall, the alarm and the power meter. A contractor or IT provider may hold a working login, never the only one.
In a new build, accounts get opened in a hurry by whoever is standing there: the contractor signs up for the alarm, an IT provider registers the domain, a family member opens the carrier account. Years later, those names show up when you change providers, bring in a partner or sell. The cleanest file starts here.
Table D. The accounts a new office opens, and who should own them
| Account | Why it matters | In whose name | Who else may hold a login |
|---|---|---|---|
| Domain registrar (your website and email address) | Whoever controls it controls your email and website | Practice or owner | IT provider, as a delegate |
| Microsoft 365 or Google Workspace administrator | Every staff mailbox and the email security settings | Practice, with the owner as a global administrator | IT provider, as a second administrator |
| Internet carrier accounts (both lines) | Moves, upgrades, outages and cancellation | Practice | Office manager as an authorized contact |
| Phone system and number porting | Your published number is a practice asset | Practice | IT provider, to manage |
| Practice-management software license | Patient records and the support contract | Practice | IT provider, as a support contact |
| Imaging software licenses (sensors, pano, CBCT) | Activation keys are needed to reinstall or move | Practice | Imaging vendor and IT provider, as support contacts |
| Firewall and Wi-Fi administrator | Remote access, guest Wi-Fi and security rules | Practice, with the credentials stored by the owner | IT provider, to manage |
| Alarm and camera system | Who can disarm the office and view recordings | Practice | Alarm contractor, as a monitoring contact |
| Power meter account | Outage alerts and billing | Practice | Office manager |
For the email piece specifically, our guide to Microsoft 365 for dental offices covers how administrator roles and email security should be set up from the start.
Ask your IT provider to hand you a one-page account register at opening: every account, whose name it is in, who has administrator access and where the recovery codes are kept. Keep it with the lease.
If this is your second or third office, set the accounts up so the next one can join them; our guide to running a multi-office dental practice across Middle Tennessee covers the site sheet and staff who float between towns. If your patients prefer a language other than English, set the preferred-language field and reminder languages before opening; see front-desk language technology in Nashville.
What must work before the first patient in a new Gallatin or Lebanon office?
Before the first patient, the readiness check must prove the whole patient path on the real internet line: check-in, charting, every sensor and the pano or CBCT opening in the chart, card payments, phones and voicemail, an electronic claim, a completed backup with one test restore, multifactor sign-in on email, and guest Wi-Fi kept separate from the office network.
Run the check at least once while the office is empty, using test patients, with the people who will do each job on opening day. Each line below is a pass or a fail, with a name next to it.
Checklist: opening-week readiness
- [ ] A test patient checked in at every front-desk station.
- [ ] A chart opened and a note saved in every operatory.
- [ ] Every intraoral sensor captures an image that lands in the right chart.
- [ ] The pano and the CBCT each send an image to the chart, and the image opens on a chairside screen.
- [ ] A card payment taken and voided on each terminal.
- [ ] Inbound and outbound calls on every phone, after-hours routing set, and voicemail picks up.
- [ ] An electronic test claim sent through the practice software.
- [ ] Email works on every staff account, with multifactor sign-in turned on.
- [ ] A full backup has run, and one file has been restored from it as a test.
- [ ] Guest Wi-Fi works and cannot reach any office computer.
- [ ] Printers and scanners work from every station that needs them.
- [ ] The battery backup shuts the server down cleanly when you unplug it as a test.
- [ ] The second internet line takes over when the first is unplugged.
- [ ] The account register from the previous section is complete.
Legend's published startup projects in Middle Tennessee include Drakes Creek Dental in Hendersonville; see the Drakes Creek Dental project page. If you are building in Rutherford County and want a provider to run this check with you, see Legend's page on dental IT support in Murfreesboro and the wider region.
How is IT priced for a new dental office in Middle Tennessee?
IT for a new office is custom quoted, because the scope depends on the drawings: the number of operatories, the imaging, the phones and the software. At Legend, hardware procurement, major cabling projects and software licensing are quoted separately. Ask any provider for the same split, so you can compare like with like.
For a new build, ask each provider to separate four things in the quote:
- One-time project work: device positions on the drawings, closet and network build, workstation setup, the readiness check.
- Hardware: computers, firewall, switches, access points, battery backup.
- Cabling, if the provider is quoting it at all, with the license number of the crew.
- Ongoing support after opening: what it covers and how it is billed.
For a full budget by line item, see our guide to the dental startup IT budget. For the design side, including how technology choices shape the floor plan, read the dental office design technology plan. Legend's overview of dental startup IT explains how its startup work is organized.
Some facts help you weigh Legend as one option. Legend Networking is headquartered in Dallas, on the same Central time as Nashville, and has served over 3,500 practices since 2004. Its published support terms read "In-house engineers; no outsourced first-level triage" and "Onsite dispatch by appointment across served dental markets; remote-first nationwide." Day-to-day software and support issues are handled remotely; cabling, installations, equipment moves and new-office build-outs are scheduled onsite by appointment. Its helpdesk is staffed 24/7 at 1-800-794-1588. Legend supports the IT environment for Dentrix, Eaglesoft, Open Dental and Archy, and for DEXIS, Vatech, Carestream, Planmeca/Romexis and Dolphin Imaging; for any other system you may run, ask. Legend holds a 4.8 rating · 173 Google reviews. Legend describes Ian Lynch, the author of this guide, as having "22 years in dental IT; oversees the NOC, onsite dispatch and client technology roadmaps."
To compare Legend with other providers, our list of the best dental IT companies sets out what to check, and the national dental IT support page describes Legend's support. If you would like a second opinion on a contractor's cabling quote or your build schedule before you sign, ask for a Free Dental IT Assessment.
What to ask your IT provider
Ask these before you sign with any IT provider for a new Middle Tennessee build, Legend included. The answers tell you whether the provider will carry the plan, or only show up at the end.
- Will you mark the device positions, the closet and the access points on our construction drawings, and when?
- Who orders the carrier, and who will be on the demarc walk with our general contractor?
- Who tests and labels the drops before the in-wall inspection, and will we get the test results?
- Which license does the cabling crew hold, and do our cameras and alarm need a separate contractor?
- What will you check the day before we open, and on which internet line?
- Which accounts will be in our name, and will we get an account register at opening?
- How do you work with our imaging vendor on the pano and CBCT install?
- What is in the one-time project quote, and what is quoted separately?
A provider that answers with names, documents and dates will run a cleaner build.
Sources
- Tennessee State Data Center (University of Tennessee): county population estimates for 2024 and 2025.
- Meharry Medical College School of Dentistry: admissions FAQs.
- Middle Tennessee Electric: fact sheet on counties served.
- Tennessee Valley Authority: local power companies, and the Cumberland EMC service area.
- Lightwave (August 2023) and the Google Fiber blog (August 2023): Murfreesboro fiber builds.
- Tennessee Board for Licensing Contractors: classification outline and the Limited Licensed Electrician page, both opened 24 November 2026.
- FCC National Broadband Map: address-level provider lookup.
Frequently asked questions
When should IT planning start for a ground-up dental office in Murfreesboro, Mt. Juliet or Spring Hill?
Start the week the lease is signed, while the floor plan can still change. That is when the internet order should go in, the power company is confirmed and the IT provider marks device positions on the drawings. Waiting until the walls are framed means the carrier date, the cabling and the closet location are set by other people's schedules instead of yours.
What if the internet provider has not built to our new shopping center yet?
Ask the landlord which carriers have built to the center, check the FCC National Broadband Map for the suite address, and call each carrier's business sales team. If no carrier has reached the suite, order anyway, get the install date in writing, and plan the build calendar around it. A temporary cellular connection can support staff training, but patient data should wait for the real line.
Who needs a Tennessee license to run data cabling in a new dental office?
Tennessee's Board for Licensing Contractors lists data cabling, alarms and security systems among its electrical specialties, and the right license can depend on the type and size of the job. Ask your general contractor and cabling contractor which license covers your scope, check the number on the Board's lookup, and confirm whether your codes department inspects the low-voltage work.
What has to be done before the in-wall inspection in a new Middle Tennessee office?
Every data drop must be run, terminated, labeled at both ends and tested, with results saved. Photograph each open wall with a tape measure in view, leave spare conduit to the demarc for a second carrier, and confirm the closet has its own circuit. After drywall, a missed drop means cutting a finished wall, so this is the last cheap moment to add cable.
Who coordinates the electrician, the cabling crew, the imaging vendor and the internet provider?
The general contractor owns the construction schedule and the inspection, and the owner signs off on the plan. The IT provider is usually best placed to coordinate the technology side: marking device positions, ordering the carrier, walking the demarc and collecting the imaging vendor's site requirements. Write the split down in a responsibility table before the first wall closes.
Which power company will serve our new suite, and does it change the UPS or electrical plan?
The name on the meter account answers it: Middle Tennessee Electric primarily serves Rutherford, Williamson and Wilson, Cumberland EMC serves Sumner, NES serves Nashville, and some towns run their own electric department. The distributor changes your outage map and alerts. The electrical plan stays the same: a dedicated closet circuit, imaging circuits to the vendor's specification, surge protection and a battery backup sized with your IT provider.
How is IT priced for a new dental office in Middle Tennessee?
It is custom quoted, because the scope depends on the drawings, the imaging and the number of operatories. At Legend, hardware procurement, major cabling projects and software licensing are quoted separately. Ask every provider to split one-time project work, hardware, cabling and ongoing support, so you can compare bids line by line.
What has to work before the first patient in a new Gallatin or Lebanon office?
The whole patient path must work on the real internet line: check-in, charting, sensors and the pano or CBCT opening in the chart, card payments, phones and voicemail, an electronic claim, a backup with one test restore, multifactor sign-in on email, and guest Wi-Fi kept apart from office computers. Run it with test patients while the office is empty.
What should a first-time owner keep in their own name from day one?
Keep every account that controls the practice in the practice's or owner's name, with the owner holding the master login: the domain, email administration, both carrier accounts, the phone numbers, the practice software and imaging licenses, the firewall, the alarm and the power meter. Providers may hold working logins. Ask for a one-page account register at opening and keep it with the lease.
The bottom line
The best time to check a build plan is before the walls close. Bring your drawings, your carrier order and this article's tables to a Free Dental IT Assessment, whether your suite is in Murfreesboro, Mt. Juliet, Spring Hill or Gallatin. If you are choosing a dental IT company in Nashville to carry the build and the years after it, start with Legend's service page for the region.