Dental Practice Acquisition IT Integration: 90 Days After Closing
The deal has closed. On Monday the acquired office opens under your name, while the server, the domain, the phone account and every vendor login still sit in the seller's, and the team has never met your IT provider. Diligence told you what you bought, not what to do first.
This guide is the second half of the acquisition. The first half, what to check before you sign, is in our dental practice acquisition IT due diligence checklist, which also holds the Day 1 to Day 30 handover worksheet. This page starts where that worksheet ends: the workstreams, the decisions, the cut-over weekend, who does what, and the tests that let you call the office integrated. It is written for the person running the integration at a group of any size, from a second office to a thirtieth.
Plan the integration as nine workstreams over about 13 weeks: access and backups first, then identity, email and phone numbers, then the network and security baseline, then vendor contracts, staff onboarding and the practice-software decision. Change one thing at a time, switch nothing off until its replacement has passed a test, and connect to shared group systems last.
- Run the integration as nine workstreams over about 13 weeks: control and backups first, then identity, email and phones, then network and security, then vendors, staff and the software decision.
- Write the migrate, keep or bridge decision for the practice software by week two, with a date and an owner, and never convert in the first 30 days.
- Treat the phone numbers as their own workstream: confirm the account holder, sign the letter of authorization, forward during the port and cancel the old service last.
- The acquired office joins the group's shared systems last, after it matches the security baseline and the network template.
- Integrated means the twelve-row acceptance sheet passes and the office appears in the monthly group report; everything else is an exception with an owner and a date.
In this guide
- What does IT integration of an acquired dental practice involve?
- Migrate, keep or bridge: which practice-software path fits the acquired office?
- The week-by-week integration checklist
- How do you take over identity, email and the domain without losing messages?
- How do you move the phone numbers and the fax line?
- What should the network and firewall standard look like at the acquired office?
- What is the minimum security baseline before the office joins shared systems?
- How do you take over vendor contracts, licences and business associate agreements?
- How do you get the acquired staff signed in and supported?
- What does the cut-over weekend plan look like?
- Who does what: the RACI for an acquired office
- How do you know the acquired office is integrated?
- What does the integration cost, and where do the lines sit?
- The IT side: how a provider runs the 90 days
- What to ask your IT provider before the acquired office joins the group
- How Legend Networking works with groups that acquire offices
- Frequently asked questions
- The bottom line
What does IT integration of an acquired dental practice involve?
IT integration means moving every system the acquired office runs on, from the server to the fax line, from the seller's control to yours, and then from "as found" to your group's standard, without stopping patient care. It is nine workstreams with their own owners and tests, not one project called "the IT changeover".
Use the table as the index to the rest of this page. Each workstream has a usual window, a "done" test and a section below. Most groups run three or four of them in the same week, so the RACI near the end matters as much as the order.
| Workstream | Done when | Usual window | Section |
|---|---|---|---|
| 1. Access and backups | Your administrators can sign in to every system; a restore has been witnessed | Week 1 | Week-by-week checklist |
| 2. Practice-software path | Migrate, keep or bridge is written down with a date and an owner | Decision by week 2; execution later | Migrate, keep or bridge |
| 3. Identity, email and domain | Every person has a named account with multi-factor sign-in; mail flows under your control | Weeks 2 to 4 | Identity, email and the domain |
| 4. Phones and numbers | Numbers ported or scheduled, fax handled, call flow documented | Weeks 3 to 8 | Phone numbers and the fax line |
| 5. Network and firewall | The office matches the group template and has a site document | Weeks 4 to 7 | Network and firewall standard |
| 6. Security baseline | Endpoint detection, backup, patching and access controls report to your console | Weeks 2 to 8 | Security baseline |
| 7. Vendors, licences and agreements | Every vendor is in the register with a status; nothing renews unseen | Weeks 1 to 9 | Vendor contracts and agreements |
| 8. Staff onboarding | Each person signs in as themselves and knows where help requests go | Weeks 2 to 5 | Onboarding the acquired team |
| 9. Acceptance and handover | The acceptance sheet passes; exceptions have owners and dates | Weeks 12 to 13 | How you know it is integrated |
Two things are deliberately not on the list. The pre-close checks (who owns the data, whether the backups restore, what the incumbent IT contract says) belong to due diligence, and if they were skipped they become week-one work. And the practice-software conversion itself is scheduled by this plan but run by its own runbook, our dental PMS migration cutover plan, because a conversion weekend has different risks from an infrastructure weekend.
Migrate, keep or bridge: which practice-software path fits the acquired office?
Decide the practice-software path in writing by the end of week two, but do not execute a conversion before day 30. Three paths exist: migrate the office onto the group's system, keep its current system with your controls around it, or bridge, keeping it for a defined period while reporting and preparation run in parallel. The table decides between them.
| Criterion | Migrate now (schedule a conversion inside the 90 days) | Keep (for at least a year, reviewed) | Bridge (keep for a defined period, then convert) |
|---|---|---|---|
| Same vendor and version as the group | Not needed; a database merge or move may be enough | Fits | Fits |
| Different vendor from the group standard | Fits when the group has converted before and staff capacity exists | Fits for a single office with stable staff | Fits for most groups: convert after the office is stable |
| Imaging bridge and sensors | Must be tested against the target software before a date is set | No change | Test during the bridge period, not on the weekend |
| Data export rights confirmed with the vendor | Required before any date | Confirm anyway; you will need it later | Required before the bridge period ends |
| Clinical and front-desk staff turnover in the first 90 days | High turnover argues against a conversion now | Fits | Fits |
| Contract end date on the current software | A near end date can force the pace; read the terms | A long remaining term argues for keep | Align the conversion date with the term end |
| Group reporting needs | Met after conversion | Met by exports or a reporting tool | Met by exports during the bridge |
| Best for | Groups on one platform with a tested conversion playbook | A second or third office whose software works and whose team is settled | Groups with mixed systems that want one platform within a year |
A bridge is not a technology; it is a decision with a date. The office keeps its software, your IT provider puts the group's backup, security and access controls around it, the billing team gets the reports it needs from exports, and the conversion is scheduled for a quiet month after the staff know you. Open Dental, for example, publishes a conversions service that includes "Data Conversions: Convert a database used by other software to an Open Dental Database" and "Database Merges: Combine multiple databases into a single database," and says that "Fees vary depending on the software you are converting from, conversion service, and other factors" (read 18 November 2026). Dentrix and Eaglesoft offices should ask Henry Schein One or Patterson in writing what converts, what is exported and on what timeline; their public pages do not state it in a form an integration lead can plan from.
Whatever the path, two things never move on closing day: the practice-management database and the imaging store. A conversion forced into the first week leaves ledgers, accounts receivable or image links behind and gives the new team no way to tell a conversion problem from a handover problem. If you are standardizing the whole group, the order of layers is in our guide to DSO technology strategy; the wider move itself is in the dental software migration checklist.
The week-by-week integration checklist
The checklist runs 13 weeks. Weeks one to four are about control and identity, five to eight about phones, network and security, nine to thirteen about vendors, the software decision and acceptance. Every row has evidence to file, because the next acquisition, your insurer and a future buyer will ask for it.
| Week | Work | Evidence to file | Exit test |
|---|---|---|---|
| 1 | Receive and test every administrator credential; create your own admin accounts; rotate the seller's; list every remote-access tool and remove the ones nobody can account for; install the group's monitoring agent; watch the practice database and some images come back from backup; confirm a backup copy exists off the premises; give staff a single help route for week one | Credential inventory with change dates; remote-tool removal list; dated restore record; agent count | You can sign in as administrator everywhere; a restore has worked in front of a witness |
| 2 | Write the practice-software decision (migrate, keep or bridge) with a date; inventory hardware with operating-system versions and ages; collect the vendor list, the phone bill, the internet contract and the registrar login; start named accounts in your directory | Decision memo; hardware inventory; vendor register draft | The decision is signed; every workstation and server is on the inventory |
| 3 | Take control of the domain registrar and DNS; decide new mailboxes or a tenant migration; open the phone port: request the customer service record, confirm the account holder, prepare the letter of authorization; collect business associate agreements in force | Registrar and DNS change log; port request date; agreements on file | You control DNS; the port request is accepted or its blocker is named |
| 4 | Move mail routing to your tenant with forwarding from the old addresses; turn on multi-factor sign-in for every account; swap shared logins for personal ones wherever the software supports it; delete accounts belonging to former staff | Mail-flow test (send and receive); account list with multi-factor status | Every current employee signs in as themselves; no former employee can |
| 5 | Train the team on the new sign-in, the ticket path and the group's security habits; publish the one-page "what changed on Monday" sheet; deploy endpoint detection to every machine; set patch windows | Training attendance; endpoint console showing every device | Every device reports to the console |
| 6 | Plan the network cut-over weekend: firewall, switches, Wi-Fi, address plan, static addresses for imaging devices; order equipment; book the window around the appointment book | Site design; equipment order; written change window | The design is approved and the window is agreed with the office manager |
| 7 | Network cut-over weekend (section below); write the site document; label the closet | Weekend runbook with results; site document | Monday smoke tests pass in every room |
| 8 | Port the phone numbers or confirm the firm port date; set call flow, voicemail and fax handling; test inbound and outbound on every line; cancel nothing until the port is confirmed | Port confirmation; call-flow document; test log | The main number rings on the new system and the old carrier confirms the port |
| 9 | Work the vendor register: assignment or new agreement for each vendor kept; termination notices for duplicates; licence transfers for practice and imaging software; confirm payer and clearinghouse portal owners | Register with a status per vendor; copies of notices | No vendor renews unseen; every portal has a named owner |
| 10 | Replace or rebuild workstations and servers marked "replace in 90 days"; retire anything on an unsupported operating system or put a dated plan on it; second test restore from the group backup | Replacement log; restore record | The office appears in the group backup and security reports with no unsupported device unaccounted for |
| 11 | If the path is migrate, run the test conversion and set the go-live date with the cutover runbook; if keep or bridge, set the review date and the reporting method | Test conversion report or review memo | A conversion date exists, or a written reason why not |
| 12 | Run the acceptance sheet (below); open the exception register for anything that failed with an owner and a date | Completed acceptance sheet; exception register | Every row is pass or has an exception entry |
| 13 | Handover meeting: what changed, what did not, what is scheduled; add the office to the monthly group report; file the evidence folder | Handover memo; first monthly report with the office on it | The office is in the monthly report and nobody is waiting on an unnamed task |
The order can compress. An office that already runs your practice software, with supported hardware and a cooperative seller, can finish in eight weeks. An office with an out-of-support server, a shared password on every workstation and a seller who kept the registrar login will take longer, and the order still holds. Hidden lines that appear during weeks nine and ten (per-location software fees, a second internet circuit, a forgotten phone line) are reconciled line by line in hidden IT costs in dental groups.
How do you take over identity, email and the domain without losing messages?
Take the registrar and DNS first, then decide between new mailboxes with forwarding and a tenant-to-tenant migration, then move mail routing in a planned window with a send-and-receive test. Every person gets a named account with multi-factor sign-in before the office joins shared systems, and shared logins are replaced where the software allows.
The registrar and DNS. The domain controls the office's email and website. Confirm whose name the registrar account is in, move it to your entity's account, and record every DNS record before you change any. If the seller keeps the domain for any reason, the purchase documents should say so and your attorney should have read that clause; the integration lead's job is to know it before week three.
New mailboxes or a tenant migration. For a one- or two-doctor office with a handful of mailboxes, creating new mailboxes in the group's tenant and forwarding the old addresses for a defined period is simpler and leaves less to go wrong. For a larger office with shared mailboxes, calendars and years of mail that staff rely on, a tenant-to-tenant migration moves the content. Microsoft's own planning guidance says to "Determine whether users keep their existing UPN or receive a new one" and to "Plan for any domain transfers between tenants," and notes the sequencing rule that "Teams content depends on Exchange mailboxes: Migrate mailboxes before or alongside Teams" (Microsoft Learn, read 18 November 2026). Either way, the test is the same: a message sent to the old address and to the new one both arrive, and a message sent from the office arrives with the right name on it. Licence tiers and tenant setup are compared in Microsoft 365 for dental offices.
Named accounts. The HIPAA Security Rule's technical safeguards include a required implementation specification to "Assign a unique name and/or number for identifying and tracking user identity" (45 CFR 164.312(a)(2)(i)). That is a description of the safeguard, not a reading of the rule for your transaction. In practice it means the "Front Desk" login the office has used for a decade is replaced by one account per person, in your directory, so that access can be granted, logged and removed by name.
Multi-factor sign-in. CISA describes multifactor authentication as "a layered approach to securing your online accounts and the data they contain." Turn it on for email, the remote-access tool, the practice software where it is offered, and every payer and vendor portal. Portals are where an acquired office's shared "billing" login usually survives longest; the fix is in our post on payer portal logins and MFA for dental groups.
What to leave alone for now. Do not rename the practice's public email addresses, change the website or move the domain's nameservers in the same week as the phone port or the network weekend. One identity change per week is enough for a front desk that is also learning a new owner.
How do you move the phone numbers and the fax line?
Treat the phone numbers as an asset with its own workstream: confirm who holds the carrier account, get a current bill and the account PIN, submit a signed letter of authorization, set call forwarding for the port window, test every line, and cancel the old service only after the new carrier confirms the port. Never cancel first.
A lost main number is the integration failure patients notice. The sequence that avoids it:
- Find the account holder. The carrier will only port a number on the instruction of the account holder of record. If that is the seller or the seller's entity, the letter of authorization needs their signature, and the purchase documents should already say the numbers transfer with the practice.
- Pull the customer service record. Ask the current carrier for the record that lists every number, line and feature on the account. Offices find forgotten lines here: an alarm line, an old fax, a credit-card terminal line.
- Match the details exactly. A mismatched address, a missing suite number or a wrong account number is enough to get a port request rejected, and the new carrier submits exactly what you give it.
- Know the timing. For the simplest case, FCC rules require that carriers "must complete a simple wireline-to-wireline or simple intermodal port request within one business day unless a longer period is requested by the new provider or by the customer" (47 CFR 52.35(a)). A business account with several numbers, a fax line and features is usually not a simple port, and the carriers set a longer window; ask the new carrier for the firm date in writing and plan week eight around it.
- Forward during the window. Set the old carrier to forward to a number you control while the port is pending, so a port that completes at midnight does not strand a morning of calls.
- Decide the fax before the port. Many offices still receive referrals and insurance documents by fax. Move it to a fax service or keep a line for it, but decide before the port date, not after the line goes quiet. Our guide to replacing old copper phone lines in a dental office covers the options.
- Test every line, both directions. Inbound to the main number, outbound caller ID shows the practice name, voicemail, after-hours routing, the fax, and any line the clinical team uses.
- Cancel last. Only after the new carrier confirms the port and the test log is complete. Cancelling the old account before the port completes can release the numbers.
If the acquired office is joining the group's phone platform, the call-flow design (hours, menu, overflow to another office) belongs in the week-six plan, and the platform choice itself is in our guide to dental phone systems.
What should the network and firewall standard look like at the acquired office?
The acquired office should match the group's site template: one firewall model and rule set, separated networks for clinical systems, business devices, imaging equipment and guests, one Wi-Fi design, fixed addresses for imaging devices and printers, protected power in the closet, and a site document. It joins the group's shared systems only after it matches.
| Element | Group standard | Why it is in the standard | Acceptance test |
|---|---|---|---|
| Firewall | One model and one rule set across offices; remote access only through the group's method | A different firewall at every office means a different exposure at every office | Rule set exported and compared with the template; no inbound rule nobody can explain |
| Network separation | Clinical workstations and servers, business devices, imaging equipment and guest Wi-Fi on separate networks | A guest phone should never reach the imaging server | A device on guest Wi-Fi cannot reach the practice server or any imaging device |
| Wi-Fi | One design: a staff network and a guest network, no shared password written on the wall | Shared Wi-Fi passwords are never changed when people leave | Staff devices authenticate as users or as enrolled devices; the guest network is isolated |
| Addressing | Fixed addresses for servers, imaging devices, printers and the phone system; a written address plan | Imaging bridges and printers break when addresses change | The address plan matches what is on the network |
| Internet | Business circuit with a known contract end; a second path (cellular or a second carrier) where phones and cloud software depend on it | A single circuit is a single point of failure for a cloud office | Failover tested: the circuit is unplugged and the phones still work |
| Closet | Rack or wall cabinet, protected power with runtime known, labels on every cable and port | An unlabelled closet with no battery backup turns a short power cut into a lost morning | Photo of the labelled closet in the site document; UPS runtime recorded |
| Site document | Diagram, address plan, equipment list with serials, carrier and vendor contacts, change log | The next technician should not need the last one | Document exists and matches the room |
Two rules make the standard safe to apply. First, the office joins group systems last: linking it to shared email, a central database or a site-to-site connection before its security matches the baseline extends its weaknesses to every location. Second, the network weekend is a planned window agreed with the office manager, not a Tuesday afternoon surprise. The design details, from cabling to closet, are in our guide to dental office network setup, and the group-wide view is in the DSO IT support services guide.
What is the minimum security baseline before the office joins shared systems?
The minimum is the set of controls your group already runs at every office, applied here before the first shared connection: endpoint detection on every machine, multi-factor sign-in on every account, a tested group backup with an off-site copy, supported operating systems or a dated plan, inventoried remote access, and a risk analysis updated for the new ownership.
| Control | What it means at the acquired office | Evidence |
|---|---|---|
| Endpoint detection and response | The group's agent on every workstation and server, replacing whatever antivirus the seller used | Console shows every inventoried device; the difference is explained in EDR vs antivirus for dental offices |
| Named accounts with multi-factor sign-in | Email, remote access, practice software where offered, portals | Account list with status; no shared login left on a clinical system without a written exception |
| Backup | The office on the group backup with an off-site copy; a second witnessed restore in week ten | Two dated restore records; see dental data backup |
| Patching and operating systems | Every device on a supported version with updates applied in a set window. For reference, Microsoft's lifecycle pages (read 18 November 2026) give October 14, 2025 as Windows 10's end of support, January 12, 2027 as the end of extended support for Windows Server 2016, and January 9, 2029 for Windows Server 2019 | Inventory shows the version per device; anything unsupported has a replacement date |
| Remote access | Every remote tool listed; the seller's and former vendors' tools removed; the group's method only | Removal list; see dental office remote access security |
| Local administrator rights | Removed from day-to-day accounts | Policy report |
| Activity review | Logs from the firewall, server and practice software reviewed on a schedule | Review log |
| Risk analysis | Updated for the office under its new ownership, with the findings feeding the exception register | Dated risk analysis document |
The risk-analysis and activity-review rows correspond to Security Rule specifications marked "Required" in the regulation text, quoted here as safeguards and not as advice: covered entities must "Conduct an accurate and thorough assessment of the potential risks and vulnerabilities to the confidentiality, integrity, and availability of electronic protected health information" (45 CFR 164.308(a)(1)(ii)(A)) and "Implement procedures to regularly review records of information system activity, such as audit logs, access reports, and security incident tracking reports" (45 CFR 164.308(a)(1)(ii)(D)). The documentation produced along the way is retained "for 6 years from the date of its creation or the date when it last was in effect, whichever is later" (45 CFR 164.316(b)(2)(i)), which is one reason the evidence column exists in every table on this page.
Unsupported machines are the common sticking point. An acquired office running Windows 10 workstations is not unusual in 2026, and the choice is replace, upgrade where the hardware allows, or isolate with a date; our guide to Windows 10 end of life for dental practices sets out the options.
How do you take over vendor contracts, licences and business associate agreements?
Build one vendor register in week two and work it to zero by week nine: every vendor that touches the office, what it touches, whose name the agreement is in, whether it can be assigned or must be re-signed, the renewal and cancel-by dates, whether a current business associate agreement exists, and who owns the portal login.
| Register column | What to record | Why |
|---|---|---|
| Vendor and what it does | Practice software, imaging, clearinghouse, phones, internet, backup, remote access, patient communication, payment processing, website, IT provider | The seller's list is never complete; the customer service record and the bank statements fill the gaps |
| Patient data | Does the vendor create, receive, maintain or transmit patient information | Decides whether a business associate agreement is needed |
| Agreement holder | The seller's entity, the seller personally, or the practice | Decides whether assignment is possible |
| Assignment or re-sign | What the agreement says about a change of ownership | Some agreements survive a sale; some end; some auto-renew |
| Renewal and cancel-by dates | Both dates, in the group calendar | Nothing should renew unseen in month two |
| Business associate agreement | In force in whose name; dated | A seller's agreement may not cover the new owner |
| Portal login owner | A named person at the group, with multi-factor sign-in | Shared portal logins outlive the people who used them |
| Decision | Keep, replace, terminate, with a date | The register is finished when every row has one |
Business associate agreements deserve a row of their own in the plan because the acquired office's agreements were made by a different covered entity. Which vendors need one, what the agreement must contain and what happens to your data when you leave a vendor are in our guide to business associate agreements for dental practices; the integration task is to know, by week nine, which agreements are in force in the right name.
The incumbent IT agreement is the register row with the most consequences. Read its term, auto-renewal and change-of-ownership language in week one if diligence did not. If it ends, the acquired office needs a support model: the group's own provider, a co-managed arrangement, or a new contract. How a shared model splits the work between an in-house IT person and an outside firm is set out in co-managed IT for dental groups. The comparison of best dental IT companies is written for that decision, and what a monthly plan should and should not include is in our guide to managed IT services for dental practices. If you are changing providers at the office, the handover steps are in how to switch dental IT providers without downtime.
How do you get the acquired staff signed in and supported?
Onboard the team in week five, after accounts exist and before the network weekend: one named account per person, a role-to-system list that says who reaches what, a single way to ask for help, a one-page "what changed on Monday" sheet, and a same-day process for removing access when someone leaves.
The acquired team has lost an owner and gained a corporate one. The IT changes land on top of that, so they should be few, explained and scheduled. What works:
- One sheet, one page. How to sign in, how multi-factor prompts work, where to click for help, what has not changed. Hand it out in a huddle, not by email to addresses that are about to move.
- A role-to-system list. Front desk, clinical, billing, office manager and provider roles, each mapped to the systems and portals the role reaches. New hires get the role; departures lose it. The method is in our dental employee IT onboarding and offboarding checklist.
- Leavers the same day. Acquisitions bring departures. The Security Rule's administrative safeguards include an addressable specification to "Implement procedures for terminating access to electronic protected health information when the employment of, or other arrangement with, a workforce member ends" (45 CFR 164.308(a)(3)(ii)(C)); the register of named accounts is what makes that possible on the day.
- Shared logins replaced with a reason. Where a clinical system cannot support one account per person, record the exception, who approved it and when it will be reviewed, instead of leaving the shared login undocumented.
- Security habits as the group does them. How to recognise a fake IT call, how to report a suspicious email, why nobody installs a remote-access tool for a vendor without a ticket.
Training is also the moment to collect what the team knows that no document holds: which sensor is temperamental, which printer the hygienists share, which vendor calls on Fridays. That goes into the site document in week seven.
What does the cut-over weekend plan look like?
The infrastructure cut-over weekend replaces the firewall, switches and Wi-Fi, enrols workstations into the group's management and moves the office onto the group's monitoring, with Monday morning smoke tests in every room. It is separate from a practice-software conversion weekend, which has its own runbook, and the two are never run together.
| When | Work | Owner | Go or roll back |
|---|---|---|---|
| Thursday | Freeze changes; confirm equipment on site; confirm the backup from Wednesday night restored; print the address plan and the smoke-test sheet; tell staff the Monday start | Integration lead | No restore record means no weekend |
| Friday after the last patient | Full backup of server and imaging store; export the old firewall configuration; photograph the closet as found | IT provider | Backup verified before any cable moves |
| Friday evening | Replace the firewall and switches; apply the template; move devices to their networks; apply fixed addresses to imaging devices, printers and the phone system | IT provider | Each device reachable from the right network before the next is moved |
| Saturday morning | Enrol workstations in the group's management; join them to the group directory if that is the standard; confirm endpoint detection and monitoring report every device | IT provider | Every inventoried device reports to the console |
| Saturday afternoon | Imaging test in every operatory: open a chart, acquire a test image on each sensor and the pano, confirm it attaches to the right record; printers, scanners, card readers, intraoral cameras | IT provider with clinical lead | Any operatory that fails is fixed or the old equipment is reconnected for that room |
| Sunday | Phones (if the port date is this weekend): inbound, outbound, voicemail, fax; remote access by the group's method; write the site document; walk the rooms with the office manager | IT provider with office manager | A failed phone test triggers forwarding to another office, not a Monday surprise |
| Sunday evening | Go or roll back decision against the sheet; a roll back means the old firewall configuration restored and the old addresses reapplied, which is why both were exported on Friday | Integration lead | Decision recorded with time and names |
| Monday, before the first patient | Technician on site or on a call an hour before opening; smoke tests re-run in every room; the office manager has one number for the day | IT provider | Open items logged as exceptions with owners |
Three habits keep the weekend short. Export before you replace, so rolling back is a file and not a rebuild. Test in the order patients will use the systems on Monday: the schedule, then the chart, then the sensor, then the claim. And give one person the decision; the rest of the room reports to them.
Who does what: the RACI for an acquired office
Give every workstream one accountable person and write it down in week one. The usual roles are the integration lead at the group, the office manager at the acquired practice, the group's IT provider, the seller and the seller's IT provider for a defined handover period, the practice-software and imaging vendors, and the attorney for the agreements.
R is responsible for doing the work, A is accountable for the result (one person per row), C is consulted, I is informed.
| Workstream | Integration lead | Office manager | IT provider | Seller and seller's IT | Software and imaging vendors | Attorney |
|---|---|---|---|---|---|---|
| Access and backups | A | I | R | C (handover) | I | I |
| Practice-software path | A | C | C | I | C | C |
| Identity, email and domain | A | I | R | C (registrar) | I | C (domain clause) |
| Phone numbers and fax | A | R (details and tests) | R (platform) | C (letter of authorization) | I | C |
| Network and firewall | I | C (window) | A and R | I | C (device addresses) | I |
| Security baseline | A | I | R | I | I | I |
| Vendors, licences and agreements | A | R (collects documents) | C | C | R (transfers) | C (assignment) |
| Staff onboarding | C | A | R | I | I | I |
| Acceptance and handover | A | C | R | I | I | I |
The row most groups get wrong is the phone port, where the office manager usually holds the bills and the account knowledge, the IT provider holds the new platform, and the seller holds the signature. One accountable person and three responsible ones is normal there; what is not normal is nobody noticing that the letter of authorization has not been signed.
How do you know the acquired office is integrated?
The office counts as integrated once each acceptance-sheet row passes or is logged as an exception with a named owner and a revisit date, and the office shows up in the group's monthly report next to the others. The sheet is twelve tests run in week twelve, in front of the office manager, with the results filed as evidence.
| # | Test | Pass means |
|---|---|---|
| 1 | Administrator access | The group can sign in to server, firewall, practice software, imaging, email tenant, registrar and phone platform; the seller and former vendors cannot |
| 2 | Restore | Two witnessed restores on record from the group backup, the latest inside 30 days |
| 3 | Identity | Every current employee has a named account with multi-factor sign-in; no former employee has any |
| 4 | Shared logins | None on a clinical system without a written exception |
| 5 | Mail sent to the old and new addresses arrives; outbound carries the right name | |
| 6 | Phones | Main number and fax tested inbound and outbound on the new platform; old account closed after confirmation |
| 7 | Network | Firewall and Wi-Fi match the template; a guest device cannot reach clinical systems; site document matches the room |
| 8 | Endpoint and monitoring | Every inventoried device reports to the console; no unsupported operating system without a dated plan |
| 9 | Imaging | Every sensor, the pano and any CBCT acquire and attach correctly from each operatory |
| 10 | Vendors | Every register row has a decision; every kept vendor has an agreement in the right name; no renewal inside 90 days is unseen |
| 11 | Practice-software path | Migrate, keep or bridge is written with a date; if migrate, the test conversion has run |
| 12 | Reporting | The office appears in the monthly group IT report with ticket counts, backup results and open exceptions |
The exception register is the companion. Every failed row becomes a line with the finding, the owner, the review date and the reason it was accepted for now. A group with three acquisitions a year ends up with a register that tells it which part of the playbook needs work.
What does the integration cost, and where do the lines sit?
Model the cost as one-time lines for the office, per-office recurring lines that change, and per-user lines that scale with headcount, and attach each to the workstream that creates it. Dollar figures depend on the office's condition and your group's standard, so get every line quoted in writing before closing where diligence allows.
| Line | Type | Created by | Note |
|---|---|---|---|
| Firewall, switches, Wi-Fi to the template | One-time | Network workstream | Often the largest single line; quote it from the diligence inventory |
| Workstations and server replacement or rebuild | One-time | Security baseline | Driven by unsupported operating systems and age |
| Cut-over weekend labour | One-time | Network workstream | Two days of engineering plus Monday on site |
| Data conversion and image conversion | One-time | Practice-software path (migrate or bridge) | Vendors publish or quote these separately; images are often a separate fee from the database |
| Phone platform licences and port fees | One-time plus per-user | Phones workstream | Port fees are usually small; the platform is per user |
| Email tenant licences | Per-user | Identity workstream | Changes with the licence tier you standardize on |
| Endpoint detection, backup, monitoring | Per-device or per-office | Security baseline | Should match what the group pays elsewhere |
| Duplicate subscriptions and lines cancelled | Saving | Vendor register | The register usually finds some |
| Ongoing support | Per-office or per-user | Vendor register (incumbent agreement decision) | The model, not the number, is decided in week nine |
The point of the model is comparison, not precision: the difference between an office that lands close to the group's standard cost and one that does not is the case for fixing the standard before the next acquisition.
The IT side: how a provider runs the 90 days
Behind the checklist, your IT provider should be running the integration as a project with a named engineer, a weekly status against the 13-week plan, and a change calendar agreed with the office manager. Six things to expect from them:
- An inventory you can read in week two: every device, operating system, age, role and replacement decision, from the monitoring agent rather than from a walk-through.
- Monitoring from day one, so the first week's problems are seen in the console before they are reported by the front desk.
- Documentation as a deliverable: the site document, the address plan, the credential inventory and the vendor register are written artefacts with dates, not knowledge in one engineer's head.
- Change windows, never changes on a clinical day without the office manager's agreement.
- Tests with witnesses: the restore, the imaging test, the phone test and the acceptance sheet are run with someone from the practice present.
- A monthly report that includes the new office from week thirteen: tickets, backup results, patching status, open exceptions.
Legend runs 24/7 monitoring at the offices it supports, with in-house engineers; no outsourced first-level triage, which matters most in week one, when the acquired team is calling a number they have never used about systems they did not choose.
What to ask your IT provider before the acquired office joins the group
About the plan
- Which of the nine workstreams will you own, and who at your company is accountable for each?
- What is your 13-week plan for this office, and which weeks need a change window on the appointment book?
- How will you report progress against it, and to whom?
About control and recovery
- When will you have tested every administrator credential, and what will you do about the ones that do not work?
- When is the first witnessed restore, and when is the second?
- Which remote-access tools did you find, and which have you removed?
About the standard
- What does our site template require at this office that it does not have today, and what does each gap cost?
- Which devices are on an unsupported operating system, and what is the date on each one?
- What test proves a guest device cannot reach clinical systems here?
About the software path
- What is your recommendation on migrate, keep or bridge for this office, and why?
- If we convert, which weekend, what is the rollback, and who runs the imaging tests?
About the acquired team
- How will the team ask for help in week one, and how will you tell them?
- How quickly is a leaver's access removed, and who confirms it?
How Legend Networking works with groups that acquire offices
Legend Networking, based in Dallas, has served over 3,500 practices since 2004: 22+ years in dental IT. The guide is written by Ian Lynch, who has 22 years in dental IT; he oversees the NOC, onsite dispatch and client technology roadmaps. On Google, Legend's rating stands at 4.8 across 173 reviews.
The week-seven imaging tests and the migrate, keep or bridge decision depend on the systems in the building; on the practice-software side Legend supports the IT environment for Dentrix, Eaglesoft, Open Dental and Archy, and on imaging for DEXIS, Vatech, Carestream, Planmeca/Romexis and Dolphin Imaging. Onsite dispatch by appointment across served dental markets; remote-first nationwide. Our DSO IT support work covers the standard an acquired office is brought to and the reporting that shows it stayed there, and our national dental IT support page describes what a practice on a Legend plan receives.
For what the second-location version of this work looks like, see the network, Wi-Fi, backup and software integration work at a practice's second location. If you are taking over a single office rather than adding to a group, our Fort Myers guide to taking over a second-generation dental office walks the same ground for one practice in one city, and the city-by-city pages are under dental IT by city.
Frequently asked questions
What is the difference between IT due diligence and IT integration in a dental practice acquisition?
Due diligence happens before you sign: it checks who owns the data, whether backups restore, what the IT contract says and what the hardware will cost to fix, so the findings can change the price or the terms. Integration happens after closing: it moves control to you and brings the office to your standard. Diligence findings become the first rows of the integration plan.
Which systems should change in the first week after closing, and which should wait?
In the first week, change only what secures control: administrator passwords, your own admin accounts, removal of unknown remote-access tools, the monitoring agent and a witnessed backup restore. Leave the practice software, the imaging bridge, the phone numbers, email addresses and workstations alone. Those move in later weeks, one at a time, each behind a test.
Can the acquired office keep its own practice management software for now?
Yes, and for most acquisitions it should, at least for the first 30 days. The decision between migrating, keeping or bridging is written down by the end of week two with a date and an owner, but a conversion is executed later, after the staff know the group and the backups, identity and network are under control. Forcing a conversion into week one mixes handover problems with conversion problems.
What does "bridging" an acquired office's software mean?
Bridging means keeping the acquired office's current practice software for a defined period while the group puts its backup, security and access controls around it, gets reporting through exports, confirms data-export rights with the vendor and prepares the conversion. The bridge ends on a date, usually aligned to the software contract term or a quiet month, when the conversion runs with its own runbook.
Who has to authorize moving the acquired office's phone numbers to the group's phone system?
The account holder of record with the current carrier, which is often the seller or the seller's entity. The new carrier needs a signed letter of authorization from that holder, a recent bill and the account PIN, with the address and account number matching the carrier's record exactly. Confirm the holder in week three so the signature is in hand before the port date.
Should the acquired team get new email addresses on closing day?
No. Email moves in week four, after accounts exist in your directory and the registrar and DNS are under your control. A small office usually gets new mailboxes with forwarding from the old addresses for a set period; a larger office with shared mailboxes and calendars may need a tenant migration. The test is that mail to both addresses arrives.
When should an acquired office connect to the group's shared network and systems?
Last. Connect the office to shared email, a central database or a site-to-site link only after it matches the group's security baseline: endpoint detection on every device, named accounts with multi-factor sign-in, a tested backup, no unknown remote access and a firewall on the template. Connecting first extends the office's weaknesses to every other location in the group.
What happens to the seller's IT contract after the practice is sold?
It depends on its term, auto-renewal and change-of-ownership language, which should have been read in diligence and must be read in week one if not. Some agreements end at the sale, some survive it, some renew unless notice is given. The register records the decision: keep for a handover period, move to the group's provider, or end it on a date.
How do you prove an acquired office is fully integrated?
Run the twelve-row acceptance sheet in week twelve with the office manager present: administrator access, two restores, named accounts, no undocumented shared logins, email, phones, network, endpoint and monitoring, imaging in every operatory, the vendor register, the software decision and the monthly report. Anything that fails goes on the exception register with a named owner and a date to revisit it.
What goes wrong most often in the first 90 days after a dental acquisition?
Four things: a phone number that stops ringing because the old account was cancelled before the port completed; a conversion forced into the first weeks that leaves ledgers or images behind; a vendor or software agreement that renews in the seller's name because nobody held the register; and an office connected to shared systems before its security matched the group's baseline.
The bottom line
If an acquisition is closing in the next quarter, or one closed last month and the checklist above has gaps, ask Legend for a Free Dental IT Assessment of the acquired office: a review of its computers, software, network security, backups and performance, with written findings and prioritized recommendations that slot straight into the 13-week plan. Start with our DSO IT support team, or read how dental IT support from Legend works for a single practice first.